347 1/2 N ORLANDO AVE 90048
Certificate Information: 347 1/2 N ORLANDO AVE 90048
- Application / Permit
- 24016-10000-40242
- Plan Check / Job No.
- B24LA37431
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE INTO A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 12/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/1/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/3/2025 | APPLICANT |
| Applicant returned to address corrections | 3/13/2025 | CARLOS MONTES |
| Plan Check Approved | 3/20/2025 | LAWRENCE QUIRANTE |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 12/5/2025 | JOSH MEISTER |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
| CofO Issued | 12/6/2025 | DEROLD HAUFF |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2025 | WALLIE JONG |
| Sewer availability | Cleared | 1/8/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2025 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 3/12/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nastarin,, Hooman; Lic. No.: C62199 | 554 S SAN VICNETE BLVD 202 LOS ANGELES, CA 90048 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/14/2025 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 4/17/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/30/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 4/30/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 4/30/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Rough | 4/30/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 4/30/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 5/7/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/7/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/7/2025 | Approved | JOSE MACIAS |
| Sewer | 5/7/2025 | Approved | JOSE MACIAS |
| Wood Frame | 5/8/2025 | Partial Inspection | RAUL BARAJAS |
| Shower Pan | 5/9/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 5/12/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/12/2025 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 5/12/2025 | Approved | JOSE MACIAS |
| Insulation | 5/14/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | BRENDAN MORELLI |
| Insulation | 5/15/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Insulation | 5/19/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 5/19/2025 | Approved | JOSE MACIAS |
| Insulation | 5/21/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 5/23/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 10/23/2025 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 10/23/2025 | Not Ready for Inspection | JOSH MEISTER |
| Smoke Detectors | 10/23/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 10/29/2025 | Approved | JOSH MEISTER |
| Final | 10/29/2025 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 10/29/2025 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Final | 10/29/2025 | Corrections Issued | JOSH MEISTER |
| PLUMBING-Final | 10/29/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 12/4/2025 | Approved | JOSH MEISTER |
| Final | 12/4/2025 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 12/4/2025 | Approved | JOSH MEISTER |
| HVAC-Final | 12/4/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 12/4/2025 | Approved | JOSH MEISTER |