3280 S MOTOR AVE 90034
Certificate Information: 3280 S MOTOR AVE 90034
- Application / Permit
- 24016-10000-40238
- Plan Check / Job No.
- B24LA37427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- EPLAN*** CHANGE OF USE OF EXISTING BIKE PARKING TO A COMMON PATIO
- Permit Issued
- Issued on 3/28/2025
- Issuing Office
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | SINA KHOSRAVI |
| Assigned to Zoning Architect | 1/2/2025 | JASON BRAVO |
| Corrections Issued | 1/8/2025 | SINA KHOSRAVI |
| Quality Review Completed | 1/9/2025 | GARO TELMI |
| Applicant returned to address corrections | 1/28/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/6/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/4/2025 | SINA KHOSRAVI |
| Plan Check Approved | 3/27/2025 | SINA KHOSRAVI |
| Issued | 3/28/2025 | APPLICANT |
| Permit Finaled | 6/17/2025 | DAVID TSAU |
| CofO Issued | 6/17/2025 | DAVID TSAU |
| Permit Finaled | 6/17/2025 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 2/11/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/11/2025 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 2/13/2025 | JULISSA LOPEZ-HODOYAN |
| Specific Plan | Cleared | 2/17/2025 | PEDRO AYALA |
| DAS Clearance | Cleared | 3/3/2025 | Kelvin Chuong |
| Zoning Plan Check | Cleared | 3/10/2025 | Kelvin Chuong |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: NA30005 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 5/28/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Smoke Detectors | 5/28/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Wood Frame | 5/28/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Final | 5/29/2025 | Conditional Approval | VASIL MIHALEV |
| Smoke Detectors | 5/29/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 5/29/2025 | Approved | VASIL MIHALEV |