10067 W RIVERSIDE DR 91602

Certificate Information: 10067 W RIVERSIDE DR 91602

Application / Permit
24016-10000-40067
Plan Check / Job No.
B24LA37170
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW GROCERY MARKET. TENANT IMPROVEMENT WITHIN AN EXISTING TYPE V SHELL BUILDING. 11,228 SQ. FT. (E) RETAIL CORE AND SHELL INTO A GROCERY.
Permit Issued
Issued on 5/19/2025
Issuing Office
Metro
Current Status
Issued on 5/19/2025

Permit Application Status History

Submitted 12/20/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 HERNAN ARREOLA
Assigned to Zoning Architect 12/26/2024 NICOLE SALEEBA
Corrections Issued 1/13/2025 HERNAN ARREOLA
Quality Review Completed 1/16/2025 PETER KIM
Building Plans Picked Up 1/21/2025 APPLICANT
Disabled Access Plans Picked Up 2/4/2025 APPLICANT
Green Plans Picked Up 4/14/2025 APPLICANT
Plan Check Approved 5/15/2025 HERNAN ARREOLA
Issued 5/19/2025 APPLICANT

Permit Application Clearance Information

Green Code Cleared 4/29/2025 DONALD CRICHLOW
Food Service Establishment Cleared 5/1/2025 STANLEY WING
"Q" conditions Cleared 5/7/2025 GEORGIA SMITH
CPC Cleared 5/7/2025 GEORGIA SMITH
CPC Cleared 5/7/2025 GEORGIA SMITH
Miscellaneous Cleared 5/7/2025 GEORGIA SMITH
ZA Case Cleared 5/7/2025 GEORGIA SMITH
ZA Case Cleared 5/7/2025 GEORGIA SMITH
ZA Case Cleared 5/7/2025 GEORGIA SMITH
Zoning Plan Check Cleared 5/8/2025 NICOLE SALEEBA
DAS Clearance Cleared 5/14/2025 EDDIE GARIN
Food establishment approval Cleared 5/15/2025 LACDHS APPROVED

Contact Information

Architect Kelley,, Kevin E; Lic. No.: C27298 611 N HARPER AVENUE      LOS ANGELES, CA 90048
Contractor Savant Construction Inc; Lic. No.: 596646-B 13830 MOUNTAIN AVENUE      CHINO, CA 91710
Engineer Baroonian,, Armen; Lic. No.: S4227 867 N FAIR OAKS AVE 100      PASADENA, CA 91103

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 5/29/2025 Conditional Approval KENNETH ROBERTS
Deputy Steel/Welding 5/30/2025 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 6/5/2025 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 6/11/2025 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 6/11/2025 Partial Approval KENNETH ROBERTS
Footing/Foundation/Slab 6/20/2025 No Access for Inspection RAFAEL CORTES
Deputy Steel/Welding 7/2/2025 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 7/3/2025 Approved JOHN KITCKO
Wood Frame 7/7/2025 Not Ready for Inspection JOHN KITCKO
Light Gage Steel Frame 7/9/2025 Partial Approval DEANDRE HOFFMAN
Insulation 7/14/2025 Partial Approval GREGORY POMISH
Insulation 7/21/2025 Partial Approval JOHN KITCKO
Wood Frame 7/25/2025 Partial Inspection JOHN KITCKO
Drywall Nailing 8/5/2025 Partial Inspection JOHN KITCKO
Partition/T-Bar Ceiling 9/4/2025 Not Ready for Inspection JOHN KITCKO
Partition/T-Bar Ceiling 9/8/2025 Partial Approval JOHN KITCKO
Partition/T-Bar Ceiling 9/12/2025 Partial Approval KENNETH ROBERTS
Special/Order Compliance 12/23/2025 Partial Inspection JOHN KITCKO
Special/Order Compliance 1/7/2026 Partial Inspection ROBERT DAVIS
Special/Order Compliance 1/15/2026 Partial Inspection ROBERT DAVIS
T-Bar Ceiling 1/21/2026 Not Ready for Inspection DEANDRE HOFFMAN
Special/Order Compliance 1/26/2026 Not Ready for Inspection GREGORY POMISH