4949 N SANCOLA AVE 91601

Certificate Information: 4949 N SANCOLA AVE 91601

Application / Permit
24016-10000-40063
Plan Check / Job No.
B24LA37160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL 2 STORY SINGLE FAMILY DWELLING. NEW KITCHEN LOCATION, GUEST BEDROOM, NEW BEDROOM, REMODEL (E) BATH (2), NEW WINDOWS, AND REWIRE AND PLUMBING. WORK PER ARCHITECT.
Permit Issued
Issued on 1/7/2025
Issuing Office
Current Status
Permit Finaled on 6/23/2025

Permit Application Status History

Submitted 12/20/2024 APPLICANT
Assigned to Plan Check Engineer 12/23/2024 NEHEMIAS RAMOS
Corrections Issued 12/26/2024 NEHEMIAS RAMOS
Building Plans Picked Up 12/30/2024 APPLICANT
Plan Check Approved 1/7/2025 DANIEL SMILEY
Issued 1/7/2025 APPLICANT
Permit Finaled 6/20/2025 JOSE AVILA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/7/2025 LEE GUILBEAUX
Sewer availability Cleared 1/7/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/7/2025 LEE GUILBEAUX

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/4/2025 Approved JOSE AVILA
Wood Frame 2/21/2025 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 3/3/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/5/2025 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/5/2025 Approved JOSE AVILA
HVAC-Rough 3/5/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/5/2025 Approved JOSE AVILA
Wood Frame 3/10/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/11/2025 Approved JOSE AVILA
HVAC-Rough 3/11/2025 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 3/24/2025 Approved JOSE AVILA
Insulation 3/26/2025 Approved JOSE AVILA
Drywall Nailing 4/1/2025 Approved JOSE AVILA
ELECTRICAL-Final 5/16/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/27/2025 Not Ready for Inspection JOSE AVILA
HVAC-Final 5/27/2025 Conditional Approval JOSE AVILA
ELECTRICAL-Final 6/2/2025 Approved JOSE AVILA
PLUMBING-Final 6/6/2025 Approved JOSE AVILA
Final 6/12/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 6/12/2025 Approved JOSE AVILA
Final 6/20/2025 Permit Finaled JOSE AVILA