155 N VISTA ST 90036

Certificate Information: 155 N VISTA ST 90036

Application / Permit
24016-10000-39937
Plan Check / Job No.
B24LA36980
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Detached 1-Story Garage conversion to ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/7/2025
Issuing Office
Current Status
CofO Issued on 5/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 DAVID CASTILLO
Corrections Issued 12/25/2024 DAVID CASTILLO
Applicant returned to address corrections 1/16/2025 DAVID CASTILLO
Applicant returned to address corrections 1/24/2025 DAVID CASTILLO
Applicant returned to address corrections 1/30/2025 DAVID CASTILLO
Applicant returned to address corrections 2/21/2025 DAVID CASTILLO
Plan Check Approved 2/28/2025 DAVID CASTILLO
Issued 3/7/2025 APPLICANT
CofO in Progress 4/29/2026 JOSH MEISTER
Permit Finaled 5/1/2026 DEROLD HAUFF
CofO Issued 5/1/2026 DEROLD HAUFF
Permit Finaled 5/1/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/4/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 1/4/2025 TREVOR QUAN
Sewer availability Cleared 1/4/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/8/2025 TREVOR QUAN
Tenant Habitability Plan Cleared 1/10/2025 HUGO GARRIDO GARZA
ZA Case Cleared 1/14/2025 MATHEW QUAN
HPOZ Cleared 2/21/2025 JORGE RUIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/4/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 4/4/2025 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/4/2025 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 4/4/2025 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Final 4/4/2025 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Rough 4/4/2025 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 4/4/2025 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 5/13/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 5/13/2025 Not Ready for Inspection BRENDAN MORELLI
METHANE-Rough 5/13/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 5/13/2025 Not Ready for Inspection BRENDAN MORELLI
Pre-Inspection 6/3/2025 Corrections Issued JOSE MACIAS
Pre-Inspection 11/6/2025 Not Ready for Inspection JOSH MEISTER
ELECTRICAL-Rough 11/26/2025 Approved JOSH MEISTER
HVAC-Rough 11/26/2025 Not Ready for Inspection JOSH MEISTER
PLUMBING-Rough 11/26/2025 Approved JOSH MEISTER
Special/Order Compliance 11/26/2025 Corrections Issued JOSH MEISTER
Deputy Drilled-In Anchors 12/19/2025 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 12/23/2025 Approved JEFFREY MEAD
Insulation 1/21/2026 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Approved JOSH MEISTER
HVAC-Rough 2/18/2026 Not Ready for Inspection JOSH MEISTER
BUILDING-Rough-Frame 3/25/2026 Corrections Issued JOSH MEISTER
Drywall Nailing 3/25/2026 Not Ready for Inspection JOSH MEISTER
Green Building Rough 3/25/2026 Approved JOSH MEISTER
HVAC-Rough 3/25/2026 Approved JOSH MEISTER
Insulation 3/25/2026 Partial Approval JOSH MEISTER
METHANE-Rough 3/25/2026 Approved JOSH MEISTER
BUILDING-Rough-Frame 4/6/2026 Approved JOSH MEISTER
Drywall Nailing 4/6/2026 Approved JOSH MEISTER
Final 4/27/2026 OK to Issue CofO JOSH MEISTER
Green Building Final 4/27/2026 Approved JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Approved JOSH MEISTER
Smoke Detectors 4/27/2026 Approved JOSH MEISTER