1515 W 49TH ST 90062

Certificate Information: 1515 W 49TH ST 90062

Application / Permit
24016-10000-39814
Plan Check / Job No.
B24LA36762
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODEL TO (E) SFD AND REMOVE PORTION IN REAR OF (E) SFD ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/11/2025
Issuing Office
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 GURUNATH NESARAJAH
Corrections Issued 12/25/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 2/1/2025 GURUNATH NESARAJAH
Applicant returned to address corrections 2/11/2025 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/13/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 2/14/2025 MIROOSH KHACHATOORIAN
Issued 4/11/2025 APPLICANT
CofO in Progress 11/3/2025 BARRY HACHE
Permit Finaled 11/10/2025 DEROLD HAUFF
CofO Issued 11/10/2025 DEROLD HAUFF
Permit Finaled 11/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/6/2025 JUSTIN BICOL
Sewer availability Cleared 2/6/2025 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/16/2025 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 6/3/2025 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 6/3/2025 Corrections Issued BARRY HACHE
HVAC-Rough 6/6/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 6/13/2025 Corrections Issued BARRY HACHE
HVAC-Rough 6/13/2025 Corrections Issued BARRY HACHE
Rough-Elec/Plmb/HVAC 6/18/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 6/24/2025 Approved BARRY HACHE
Green Building Rough 6/24/2025 Approved BARRY HACHE
PLUMBING-Rough 6/24/2025 Approved BARRY HACHE
Insulation 7/8/2025 Approved BARRY HACHE
Interior/Exterior Lathing 7/22/2025 Partial Approval BARRY HACHE
Interior/Exterior Lathing 7/28/2025 Approved BARRY HACHE
Drywall Nailing 8/4/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 10/15/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 10/15/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 10/15/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 10/21/2025 Not Ready for Inspection BARRY HACHE
Final 10/21/2025 Corrections Issued BARRY HACHE
HVAC-Final 10/21/2025 Approved BARRY HACHE
PLUMBING-Final 10/21/2025 Approved BARRY HACHE
ELECTRICAL-Final 10/24/2025 Approved BARRY HACHE
Final 10/24/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 10/24/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 10/24/2025 Corrections Issued BARRY HACHE
Final 10/29/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved BARRY HACHE
Service/Power Release 10/29/2025 Approved BARRY HACHE
Smoke Detectors 10/29/2025 Approved BARRY HACHE
Final 11/3/2025 OK to Issue CofO BARRY HACHE