1332 S BARRY AVE 90025
Certificate Information: 1332 S BARRY AVE 90025
- Application / Permit
- 24016-10000-39760
- Plan Check / Job No.
- B24LA36677
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: (1) new special steel cantilever column , (1) new wood shear wall & (4)-new hardy panels
- Permit Issued
- Issued on 3/28/2025
- Issuing Office
- Current Status
- CofC Issued on 9/2/2025
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | HANS SANTIAGO |
| Corrections Issued | 12/23/2024 | HANS SANTIAGO |
| Quality Review Completed | 12/23/2024 | CHARMIE HUYNH |
| Applicant returned to address corrections | 1/19/2025 | HANS SANTIAGO |
| Plan Check Approved | 1/22/2025 | ANDREW SANTIAGO |
| Issued | 3/28/2025 | APPLICANT |
| OK for CofC | 8/22/2025 | RICARDO ROBLES |
| CofC Issued | 9/2/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/27/2025 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | One Stop Retrofit; Lic. No.: 1026051-B | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2025 | Approved | VASIL MIHALEV |
| Deputy Steel/Welding | 5/30/2025 | Partial Approval | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Footing/Foundation/Slab | 6/5/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Structural Steel Frame | 6/5/2025 | Not Ready for Inspection | CASIMIR BRITTON |
| Wood Frame | 6/5/2025 | Partial Approval | CASIMIR BRITTON |
| Deputy Drilled-In Anchors | 6/12/2025 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 6/12/2025 | Approved | VASIL MIHALEV |
| Insulation | 6/12/2025 | Approved | VASIL MIHALEV |
| Structural Steel Frame | 6/12/2025 | Approved | VASIL MIHALEV |
| Wood Frame | 6/12/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 6/13/2025 | Conditional Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 6/26/2025 | Conditional Approval | RICARDO ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Approved | DANIEL VARNUM |
| Wood Frame | 6/27/2025 | Approved | DANIEL VARNUM |
| Drywall Nailing | 7/23/2025 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 7/23/2025 | Approved | RICARDO ROBLES |
| Final | 8/22/2025 | OK for CofC | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 8/22/2025 | Approved | RICARDO ROBLES |