1030 1/2-3/4 E 46TH ST 90011
Certificate Information: 1030 1/2-3/4 E 46TH ST 90011
- Application / Permit
- 24016-10000-39569
- Plan Check / Job No.
- B24LA36370
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF EXISTING SFD TO ADU (524 SF) PER (Attached ADU Contained in Existing SFD per State Law,CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Metro
- Current Status
- Issued on 3/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2024 | AUNG SOE |
| Corrections Issued | 12/24/2024 | AUNG SOE |
| Building Plans Picked Up | 12/26/2024 | APPLICANT |
| Applicant returned to address corrections | 2/21/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 3/6/2025 | CARLOS MONTES |
| Plan Check Approved | 3/20/2025 | CRISTINA SALAZAR |
| Issued | 3/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 1/31/2025 | JESSICA OPINION |
| Tenant Habitability Plan | Cleared | 3/17/2025 | KORNEL LELEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/2/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/25/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/19/2025 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/19/2025 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/19/2025 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 9/25/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 9/25/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 9/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 9/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/3/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 10/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/9/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/20/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/2/2026 | Approved | ALEX COLIN |
| HVAC-Final | 6/1/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/1/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |