2809 N VAQUERO AVE 90032
Certificate Information: 2809 N VAQUERO AVE 90032
- Application / Permit
- 24016-10000-39497
- Plan Check / Job No.
- B24LA36232
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED GARAGE TO ADU PER LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 3/29/2025
- Issuing Office
- Current Status
- CofO Issued on 11/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | VIVIAN LAO |
| Corrections Issued | 1/8/2025 | VIVIAN LAO |
| Quality Review Completed | 1/9/2025 | GARO TELMI |
| Applicant returned to address corrections | 2/27/2025 | VIVIAN LAO |
| Plan Check Approved | 3/28/2025 | VIVIAN LAO |
| Issued | 3/29/2025 | APPLICANT |
| CofO in Progress | 11/14/2025 | LILIANA PORTILLO |
| Permit Finaled | 11/15/2025 | DEROLD HAUFF |
| CofO Issued | 11/15/2025 | DEROLD HAUFF |
| Permit Finaled | 11/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/4/2025 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 2/11/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 2/18/2025 | VIVIAN LAO |
Contact Information
| Contractor | Proud Crowd Inc The; Lic. No.: 1074719-B | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/2/2025 | Partial Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 5/2/2025 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 5/2/2025 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 5/12/2025 | Approved | REGINA MENDEZ |
| Footing/Foundation/Slab | 5/20/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/6/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/7/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 7/7/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/7/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/8/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/8/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/9/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 7/9/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Approved | BRENDAN MORELLI |
| Insulation | 7/15/2025 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/15/2025 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 7/23/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 7/23/2025 | Approved | LILIANA PORTILLO |
| Insulation | 7/23/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/8/2025 | Approved | GEM DE OCAMPO |
| Final | 10/9/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/9/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV No Gas | LILIANA PORTILLO |
| Smoke Detectors | 10/9/2025 | Approved | LILIANA PORTILLO |
| Final | 10/16/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/13/2025 | Approved | LILIANA PORTILLO |
| Final | 11/13/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 11/13/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/13/2025 | Approved | LILIANA PORTILLO |