808 S WESTERN AVE 90005
Certificate Information: 808 S WESTERN AVE 90005
- Application / Permit
- 24016-10000-39390
- Plan Check / Job No.
- B24LA36111
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Night Club
- Work Description
- *ePlan* Change of occupancy from message parlor to karaoke establishment
- Permit Issued
- Issued on 8/5/2025
- Issuing Office
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | MATTHEW TORRES |
| Assigned to Zoning Architect | 12/26/2024 | NEVRIK NAVASARTIAN |
| Corrections Issued | 1/3/2025 | MATTHEW TORRES |
| Quality Review Completed | 1/7/2025 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/24/2025 | MATTHEW TORRES |
| Applicant returned to address corrections | 3/26/2025 | MATTHEW TORRES |
| Plan Check Approved | 8/4/2025 | MATTHEW TORRES |
| No Progress | 8/5/2025 | MATTHEW TORRES |
| Plan Check Approved | 8/5/2025 | MATTHEW TORRES |
| Issued | 8/5/2025 | APPLICANT |
| CofO in Progress | 2/23/2026 | PAUL BAZERKANIAN |
| Permit Finaled | 3/20/2026 | ERNESTO CORRAL |
| CofO Issued | 3/20/2026 | ERNESTO CORRAL |
| Permit Finaled | 3/20/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Hold | Cleared | 1/6/2025 | MARIA VENDIVIL |
| Sewer availability | Cleared | 1/10/2025 | ADRIAN SANCHEZ |
| Miscellaneous | Cleared | 1/14/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/14/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/14/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/14/2025 | JACQUELINE TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | PAMELA TENEZA |
| Historic Resource Verification | Cleared | 2/11/2025 | RAFAEL FONTES |
| Miscellaneous | Cleared | 2/11/2025 | RUBEN VASQUEZ |
| Redevelopment Project Area | Cleared | 2/18/2025 | YASMINE BASHIRI |
| Green Code | Cleared | 4/18/2025 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 6/17/2025 | Jesse Arellano |
| Fire Marshal Fire Life Safety | Cleared | 6/23/2025 | MENOA AGHAJANI |
| Zoning Plan Check | Cleared | 7/28/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Architect | Colon,, Jorge Jose; Lic. No.: NA39951 | , |
| Contractor | Holwick Constructors Inc; Lic. No.: 766151-B | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/15/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 9/19/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/22/2025 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 9/22/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/25/2025 | Approved | ALFREDO LOPEZ |
| Wood Frame | 9/26/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 9/29/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/1/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 10/1/2025 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/1/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/6/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/9/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 10/9/2025 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/9/2025 | Approved | JEROME BLACKWOOD |
| Drywall Nailing | 10/10/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 10/10/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/17/2025 | Partial Approval | LARRY ARNICK |
| Light Gage Steel Frame | 10/31/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| T-Bar Ceiling | 12/1/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 12/15/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 12/23/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 12/31/2025 | Partial Inspection | PAUL BAZERKANIAN |
| Final | 1/8/2026 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Green Building Final | 1/8/2026 | Approved | PAUL BAZERKANIAN |
| Green Building Rough | 1/8/2026 | Approved | PAUL BAZERKANIAN |
| Reinforced Concrete Frame | 1/8/2026 | Partial Approval | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 1/8/2026 | Approved | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 1/23/2026 | Partial Approval | IAN BLINN |
| Final | 1/29/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 1/29/2026 | Partial Inspection | JONATHAN CLARKE |
| Reinforced Concrete Frame | 1/29/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 1/30/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Reinforced Concrete Frame | 1/30/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 2/23/2026 | Partial Approval | PAUL BAZERKANIAN |
| Final | 2/23/2026 | OK to Issue CofO | PAUL BAZERKANIAN |
| Reinforced Concrete Frame | 2/23/2026 | Approved | PAUL BAZERKANIAN |