8664 W AIRDROME ST 90035
Certificate Information: 8664 W AIRDROME ST 90035
- Application / Permit
- 24016-10000-39209
- Plan Check / Job No.
- B24LA35795
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Convert Detached Rec.Room and Portion of Garage to ADU per GCS 65852.2(e)(1)(A)., Remaining portion of Garage to be converted to Storgae. All Work per WFPP
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- Issued on 8/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2024 | DAVID CASTILLO |
| Corrections Issued | 12/21/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/4/2025 | DAVID CASTILLO |
| Plan Check Approved | 7/27/2025 | DAVID CASTILLO |
| Issued | 8/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2025 | ERIK BEASLEY |
| Permit | Cleared | 3/22/2025 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/22/2025 | ERIK BEASLEY |
| CPC | Cleared | 3/27/2025 | ALEX VELA |
| CPC | Cleared | 3/27/2025 | ALEX VELA |
| CPC | Cleared | 3/27/2025 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 12/8/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/24/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 12/24/2025 | Corrections Issued | EVAN COOPER |
| Insulation | 12/24/2025 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 12/24/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 12/24/2025 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 12/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 12/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 12/26/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 12/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/26/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/11/2026 | Corrections Issued | WILBER ROSALES |
| Insulation | 2/11/2026 | Partial Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/4/2026 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Rough | 3/4/2026 | Not Ready for Inspection | WILBER ROSALES |
| METHANE-Rough | 3/4/2026 | Corrections Issued | WILBER ROSALES |