3015 E FUTURE PL 90065
Certificate Information: 3015 E FUTURE PL 90065
- Application / Permit
- 24016-10000-39205
- Plan Check / Job No.
- B24LA35791
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Remodel front single family dwelling. Work per WFPP.
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/31/2025
Permit Application Status History
| Submitted | 12/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 12/18/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 2/10/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/13/2025 | NEHEMIAS RAMOS |
| Issued | 2/14/2025 | APPLICANT |
| Permit Finaled | 10/30/2025 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/29/2025 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 1/31/2025 | JESSICA OPINION |
Contact Information
| Contractor | Atp Development & Construction; Lic. No.: 1092130-B | , |
| Contractor | North By Northwest Commercial Inc; Lic. No.: 1092130-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/19/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 3/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 3/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 4/21/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/21/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/17/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/22/2025 | Approved | REGINA MENDEZ |
| Insulation | 7/22/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 7/22/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 7/28/2025 | Approved | AMY COLIN |
| Shower Pan | 7/28/2025 | Approved | AMY COLIN |
| Underground Mechanical | 9/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 9/24/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/24/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/30/2025 | Permit Finaled | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/30/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 10/30/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/30/2025 | Approved | ALIZAH MAYAGOITIA |