3015 E FUTURE PL 90065

Certificate Information: 3015 E FUTURE PL 90065

Application / Permit
24016-10000-39205
Plan Check / Job No.
B24LA35791
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Remodel front single family dwelling. Work per WFPP.
Permit Issued
Issued on 2/14/2025
Issuing Office
Current Status
Permit Finaled on 10/31/2025

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/17/2024 JOSE VELAZQUEZ
Corrections Issued 12/18/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 2/10/2025 NEHEMIAS RAMOS
Plan Check Approved 2/13/2025 NEHEMIAS RAMOS
Issued 2/14/2025 APPLICANT
Permit Finaled 10/30/2025 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Specific Plan Cleared 1/29/2025 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 1/31/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 1/31/2025 JESSICA OPINION

Contact Information

Contractor Atp Development & Construction; Lic. No.: 1092130-B       ,
Contractor North By Northwest Commercial Inc; Lic. No.: 1092130-B       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/19/2025 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 3/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 3/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Underground Mechanical 3/10/2025 Approved ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 4/21/2025 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 4/21/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/17/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/17/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 7/17/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 7/17/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 7/22/2025 Approved REGINA MENDEZ
Insulation 7/22/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 7/22/2025 Approved REGINA MENDEZ
Drywall Nailing 7/28/2025 Approved AMY COLIN
Shower Pan 7/28/2025 Approved AMY COLIN
Underground Mechanical 9/4/2025 Approved ALIZAH MAYAGOITIA
Gas Test 9/24/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/30/2025 Approved ALIZAH MAYAGOITIA
Final 10/30/2025 Permit Finaled ALIZAH MAYAGOITIA
HVAC-Final 10/30/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 10/30/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 10/30/2025 Approved ALIZAH MAYAGOITIA