1411 N HIGHLAND AVE STE A 90028

Certificate Information: 1411 N HIGHLAND AVE STE A 90028

Application / Permit
24016-10000-39111
Plan Check / Job No.
B24LA35624
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE AND TENANT IMPROVEMENT FROM RETAIL TO BEAUTY SHOP (NAIL SALON). WORK INCLUDES NEW PARTITIONS, FINISHES AND MILLWORK. AREA OF WORK 1260 SF
Permit Issued
Issued on 1/27/2025
Issuing Office
Metro
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 ADAM HEGAZI
Corrections Issued 12/14/2024 ADAM HEGAZI
Building Plans Picked Up 12/18/2024 APPLICANT
Plan Check Approved 1/15/2025 EDWIN MARTINEZ
Issued 1/27/2025 APPLICANT
CofO in Progress 7/21/2025 TIMOTHY POWELL
Permit Finaled 11/4/2025 ERNESTO CORRAL
CofO Issued 11/4/2025 ERNESTO CORRAL
Permit Finaled 11/4/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2024 ERIK BEASLEY
Sewer availability Cleared 12/31/2024 ERIK BEASLEY
ZA Case Cleared 1/2/2025 DANIEL CORONADO
ZA Case Cleared 1/2/2025 DANIEL CORONADO
"Q" conditions Cleared 1/7/2025 DANIEL CORONADO
CPC Cleared 1/7/2025 DANIEL CORONADO
Historic Resource Verification Cleared 1/10/2025 YASMINE BASHIRI
Redevelopment Project Area Cleared 1/10/2025 YASMINE BASHIRI

Contact Information

Architect , ; Lic. No.: C35911       ,
Contractor Jade Construction Llc; Lic. No.: 1115106-B 798 MANLEY DR      SAN GABRIEL, CA 91776

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 3/3/2025 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 4/23/2025 Partial Approval CHRISTOPHER BLACKWOOD
Final 7/9/2025 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 7/9/2025 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved TIMOTHY POWELL
Smoke Detectors 7/9/2025 Approved TIMOTHY POWELL
Final 7/18/2025 OK to Issue CofO TIMOTHY POWELL