1000 W VIN SCULLY AVE 7th Level 90012
Certificate Information: 1000 W VIN SCULLY AVE 7th Level 90012
- Application / Permit
- 24016-10000-39102
- Plan Check / Job No.
- B24LA35617
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Stadium (unlimited seating capacity)
- Work Description
- Level 7 Improvements - 5,955 sf structure to included Team Store, Concession, and First Aid Room. Update entry gates and add adult changing table
- Permit Issued
- Issued on 12/17/2025
- Issuing Office
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 9/25/2025 | NEVRIK NAVASARTIAN |
| Corrections Issued | 10/3/2025 | HERNAN ARREOLA |
| Quality Review Completed | 10/16/2025 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 12/17/2025 | HERNAN ARREOLA |
| Issued | 12/17/2025 | APPLICANT |
| CofO in Progress | 3/20/2026 | ERNESTO CORRAL |
| Permit Finaled | 3/20/2026 | ERNESTO CORRAL |
| CofO Issued | 3/20/2026 | ERNESTO CORRAL |
| Permit Finaled | 3/20/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/9/2025 | MAYELA VILLA |
| Miscellaneous | Cleared | 10/9/2025 | MAYELA VILLA |
| ZA Case | Cleared | 10/9/2025 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 10/31/2025 | JEREMY CHOK |
| Green Code | Cleared | 11/13/2025 | Luke Gonzales |
| Fire Marshal Fire Life Safety | Cleared | 11/23/2025 | MENOA AGHAJANI |
| ZI | Cleared | 11/26/2025 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 12/5/2025 | Luke Gonzales |
| CPC | Cleared | 12/11/2025 | RUBEN VASQUEZ |
| Zoning Plan Check | Cleared | 12/16/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Architect | Levin,, Brenda A; Lic. No.: C11323 | 700 S FLOWER STREET SUITE 575 LOS ANGELES, CA 90017 |
| Contractor | Pcl Construction Services Inc; Lic. No.: 474555-B | , |
| Engineer | Wilkerson,, Ryan Lee; Lic. No.: S4728 | 20734 SARDINIA WAY PORTER RANCH, CA 91326 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Approved | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/2/2026 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 1/2/2026 | Corrections Issued | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/5/2026 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 1/5/2026 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 1/5/2026 | Partial Approval | SCOTT SOBEL |
| Drywall Nailing | 1/9/2026 | Partial Approval | RONALD JIMENEZ |
| Insulation | 1/9/2026 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/14/2026 | Corrections Issued | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/21/2026 | Not Ready for Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/22/2026 | Partial Approval | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 1/27/2026 | Conditional Approval | RONALD JIMENEZ |
| Deputy Fireproofing | 1/27/2026 | Conditional Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 1/27/2026 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/30/2026 | Partial Approval | RONALD JIMENEZ |
| Deputy Fireproofing | 2/2/2026 | Conditional Approval | REGINA MENDEZ |
| Light Gage Steel Frame | 2/2/2026 | Partial Approval | REGINA MENDEZ |
| Light Gage Steel Frame | 2/6/2026 | Partial Approval | REGINA MENDEZ |
| T-Bar Ceiling | 2/13/2026 | Not Ready for Inspection | SEAN POMISH |
| Interior/Exterior Lathing | 2/18/2026 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/24/2026 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/26/2026 | Not Ready for Inspection | SEAN POMISH |
| Light Gage Steel Frame | 3/3/2026 | Corrections Issued | RONALD JIMENEZ |
| Light Gage Steel Frame | 3/4/2026 | Partial Approval | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 3/5/2026 | Partial Approval | SEAN POMISH |
| Deputy Steel/Welding | 3/5/2026 | Partial Approval | SEAN POMISH |
| Light Gage Steel Frame | 3/5/2026 | Partial Inspection | SEAN POMISH |
| Deputy Reinf. Concrete | 3/6/2026 | Partial Approval | SEAN POMISH |
| Deputy Steel/Welding | 3/6/2026 | Partial Approval | SEAN POMISH |
| T-Bar Ceiling | 3/6/2026 | Partial Approval | SEAN POMISH |
| T-Bar Ceiling | 3/12/2026 | Approved | RONALD JIMENEZ |
| Final | 3/17/2026 | Partial Inspection | SEAN POMISH |
| Green Building Final | 3/17/2026 | Approved | SEAN POMISH |
| Green Building Rough | 3/17/2026 | Approved | SEAN POMISH |
| METHANE-Final | 3/17/2026 | Approved | SEAN POMISH |
| METHANE-Rough | 3/17/2026 | Approved | SEAN POMISH |
| Reinforced Concrete Frame | 3/17/2026 | Approved | SEAN POMISH |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Approved | SEAN POMISH |
| Smoke Detectors | 3/17/2026 | Approved | SEAN POMISH |
| Verify Sprinkler Sign Off | 3/17/2026 | Approved | SEAN POMISH |
| Final | 3/19/2026 | Partial Inspection | ERNESTO CORRAL |
| Final | 3/20/2026 | OK to Issue CofO | ERNESTO CORRAL |