2556 S BENTLEY AVE 90064

Certificate Information: 2556 S BENTLEY AVE 90064

Application / Permit
24016-10000-38940
Plan Check / Job No.
B24LA35416
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of (E) detached Garage into ADU per state law GCS 66323(a)(1)
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 9/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/13/2024 MINA HABILI
Corrections Issued 12/16/2024 MINA HABILI
Applicant returned to address corrections 2/22/2025 MINA HABILI
Plan Check Approved 3/4/2025 MINA HABILI
Issued 3/6/2025 APPLICANT
CofO in Progress 9/26/2025 MICHAEL PELHAM
Permit Finaled 9/29/2025 RICHARD STEINBACH
CofO Issued 9/29/2025 RICHARD STEINBACH
Permit Finaled 9/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 1/28/2025 STEVEN WECHSLER
Address approval Cleared 2/5/2025 DIANA RENTERIA
Sewer availability Cleared 2/5/2025 DIANA RENTERIA
Specific Plan Cleared 2/12/2025 FREDDY GARCIA
Grading Pre-Inspection Cleared 2/14/2025 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 2/28/2025 LIAM ODONOVAN

Contact Information

Contractor Owner-Builder       ,
Engineer Howe,, Carl William; Lic. No.: NA44773       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/10/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 6/10/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/10/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/2/2025 Partial Approval WILBER ROSALES
Sewer 7/2/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 7/11/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/11/2025 Approved ARAM AVEDISIAN
Green Building Rough 7/11/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 7/11/2025 Approved ARAM AVEDISIAN
MERV13>=Rough 7/11/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/11/2025 Approved ARAM AVEDISIAN
Insulation 7/17/2025 Approved JAYLIN GRAVITTE
Shower Pan 7/17/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 7/21/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/21/2025 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 8/1/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 9/15/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 9/15/2025 Approved MICHAEL ALLEN
Final 9/15/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 9/15/2025 Approved MICHAEL ALLEN
Green Building Rough 9/15/2025 Approved MICHAEL ALLEN
HVAC-Final 9/15/2025 Approved MICHAEL ALLEN
MERV13>=Final 9/15/2025 Approved MICHAEL ALLEN
PLUMBING-Final 9/15/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved MICHAEL ALLEN
Service/Power Release 9/15/2025 Approved MICHAEL ALLEN
Smoke Detectors 9/15/2025 Approved MICHAEL ALLEN
Final 9/25/2025 OK to Issue CofO MICHAEL PELHAM