6302 1/2 S RIMPAU BLVD 90043

Certificate Information: 6302 1/2 S RIMPAU BLVD 90043

Application / Permit
24016-10000-38922
Plan Check / Job No.
B24LA35390
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing detached garage to ADU PER GCS 65852.2(e)(1)(A). Work per WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 10/07/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 3/3/2025
Issuing Office
Current Status
CofO Issued on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/13/2024 ALEXANDER JOO
Corrections Issued 12/13/2024 ALEXANDER JOO
Plan Check Approved 2/27/2025 CRYSTEL MAALOUF
Issued 3/3/2025 APPLICANT
CofO in Progress 3/16/2026 MICHAEL SERETTI
Permit Finaled 3/16/2026 CLAUDIO MORENO
CofO Issued 3/16/2026 CLAUDIO MORENO
Permit Finaled 3/16/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 1/9/2025 CELINA MORENO
Sewer availability Cleared 1/9/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/14/2025 CELINA MORENO
Construction near power lines Cleared 2/13/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/21/2025 Approved MICHAEL SERETTI
ELECTRICAL-Rough 8/21/2025 Approved MICHAEL SERETTI
Footing/Foundation/Slab 8/21/2025 Approved MICHAEL SERETTI
Green Building Rough 8/21/2025 Approved MICHAEL SERETTI
HVAC-Rough 8/21/2025 Approved MICHAEL SERETTI
PLUMBING-Rough 8/21/2025 Approved MICHAEL SERETTI
PLUMBING-Final 9/18/2025 Approved MICHAEL SERETTI
Drywall Nailing 10/9/2025 Approved MICHAEL SERETTI
ELECTRICAL-Final 10/9/2025 Approved MICHAEL SERETTI
Final 10/9/2025 OK to Issue CofO MICHAEL SERETTI
Gas Test 10/9/2025 Approved MICHAEL SERETTI
Green Building Final 10/9/2025 Approved MICHAEL SERETTI
HVAC-Final 10/9/2025 Approved MICHAEL SERETTI
Interior/Exterior Lathing 10/9/2025 Approved MICHAEL SERETTI
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved MICHAEL SERETTI
Shower Pan 10/9/2025 Approved MICHAEL SERETTI
Smoke Detectors 10/9/2025 Approved MICHAEL SERETTI