1008 S BROXTON AVE 90024
Certificate Information: 1008 S BROXTON AVE 90024
- Application / Permit
- 24016-10000-38831
- Plan Check / Job No.
- B24LA35243
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- **ePlan** **COMBINE SIX EXISTING TENANT SPACES FOR CONSTRUCTION OF A NEW RESTAURANT IN AN EXISTING BUILDING. TENANT IMPROVEMENT ONLY. NO CHANGE OF USE. SEE COMMENTS.
- Permit Issued
- Issued on 9/16/2025
- Issuing Office
- Current Status
- Issued on 9/16/2025
Permit Application Status History
| Submitted | 12/11/2024 | APPLICANT |
| Assigned to Zoning Architect | 12/12/2024 | RONALD GREENE |
| Assigned to Plan Check Engineer | 12/12/2024 | JOHNNY WU |
| Corrections Issued | 1/7/2025 | JOHNNY WU |
| Quality Review Completed | 1/13/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 2/24/2025 | JOHNNY WU |
| Applicant returned to address corrections | 3/18/2025 | JOHNNY WU |
| Applicant returned to address corrections | 5/29/2025 | JOHNNY WU |
| Applicant returned to address corrections | 6/27/2025 | JOHNNY WU |
| Applicant returned to address corrections | 9/12/2025 | JOHNNY WU |
| Plan Check Approved | 9/12/2025 | JOHNNY WU |
| Issued | 9/16/2025 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/19/2024 | Ricardo Ramirez Solis |
| Encroachment in public way | Cleared | 1/31/2025 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 2/14/2025 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2025 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 2/19/2025 | VLADIMIR ARUTYUNYAN |
| Green Code | Cleared | 3/16/2025 | Ricardo Ramirez Solis |
| Specific Plan | Cleared | 3/26/2025 | HAMID GHAEMMAGHAMI |
| Fire Marshal Fire Life Safety | Cleared | 4/23/2025 | FIRE DEPARTMENT |
| Miscellaneous | Cleared | 7/10/2025 | MAYELA VILLA |
| Miscellaneous | Cleared | 7/10/2025 | MAYELA VILLA |
| Specific Plan | Cleared | 7/10/2025 | MAYELA VILLA |
| Food Service Establishment | Cleared | 7/16/2025 | CRYSTOL BRANDT |
| Zoning Plan Check | Cleared | 8/29/2025 | Ronald Greene |
| Food establishment approval | Cleared | 9/12/2025 | LACDHS APPROVED |
Contact Information
| Architect | Sola,, Javier M; Lic. No.: C34682 | 1628 FREEMAN AVENUE LONG BEACH, CA 90804 |
| Contractor | Embree Construction Group Inc; Lic. No.: 488503-B | , |
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
| Engineer | Ferrer,, Eric Joseph Rabano; Lic. No.: C97020 | 12651 ARTESIA BLVD APT 340 CERRITOS, CA 90703 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/10/2025 | Partial Approval | VASIL MIHALEV |
| Footing/Foundation/Slab | 10/10/2025 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/16/2025 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 10/29/2025 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 10/30/2025 | Conditional Approval | RICARDO ROBLES |
| Footing/Foundation/Slab | 11/3/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Reinf. Concrete | 11/19/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 11/26/2025 | Conditional Approval | DANIEL VARNUM |
| Pre-Inspection | 12/2/2025 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 12/2/2025 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 12/8/2025 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 12/12/2025 | Conditional Approval | RICARDO ROBLES |
| Drywall Nailing | 12/15/2025 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 12/15/2025 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 12/18/2025 | Partial Inspection | PAUL DAVIDSON |
| Wood Frame | 12/18/2025 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 12/24/2025 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 1/6/2026 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/12/2026 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 1/13/2026 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 1/20/2026 | Partial Approval | CASIMIR BRITTON |
| Drywall Nailing | 2/10/2026 | Partial Approval | ROGELIO REYNA |
| Deputy Drilled-In Anchors | 2/12/2026 | Conditional Approval | ROGELIO REYNA |
| Footing/Foundation/Slab | 2/12/2026 | Approved | ROGELIO REYNA |
| Deputy Reinf. Concrete | 2/13/2026 | Approved | DERRICK SPENCER |
| Wood Frame | 2/23/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| Drywall Nailing | 3/3/2026 | Partial Approval | DANIEL VARNUM |
| Insulation | 3/19/2026 | Partial Approval | PAUL DAVIDSON |
| Insulation | 3/27/2026 | Approved | ROGELIO REYNA |
| Interior/Exterior Lathing | 4/1/2026 | Conditional Approval | ROGELIO REYNA |
| Drywall Nailing | 4/7/2026 | Approved | ROGELIO REYNA |
| Drywall Nailing | 4/10/2026 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 4/15/2026 | Approved | ROGELIO REYNA |
| Footing/Foundation/Slab | 4/22/2026 | Not Ready for Inspection | ROGELIO REYNA |
| Partition/T-Bar Ceiling | 4/22/2026 | Not Ready for Inspection | ROGELIO REYNA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2026 | Approved | ROGELIO REYNA |
| Footing/Foundation/Slab | 4/24/2026 | Approved | ROGELIO REYNA |
| Partition/T-Bar Ceiling | 4/28/2026 | Not Ready for Inspection | ROGELIO REYNA |
| Partition/T-Bar Ceiling | 5/6/2026 | Not Ready for Inspection | ROGELIO REYNA |
| Pre-Inspection | 5/21/2026 | Partial Inspection | ROGELIO REYNA |