11004 W BELLAGIO PL 90077

Certificate Information: 11004 W BELLAGIO PL 90077

Application / Permit
24016-10000-38737
Plan Check / Job No.
B24LA35128
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Interior renovation and addition of an interior elevator to an existing single-family residence. INTERIOR REMODEL ONLY, NO SQFT ADDED
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
Permit Finaled on 1/8/2026

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 KHUONG TRUONG
Corrections Issued 12/19/2024 KHUONG TRUONG
Quality Review Completed 12/23/2024 GARO TELMI
Applicant returned to address corrections 1/14/2025 KHUONG TRUONG
Plan Check Approved 2/4/2025 KHUONG TRUONG
Issued 2/4/2025 APPLICANT
Permit Finaled 1/7/2026 EVAN COOPER

Permit Application Clearance Information

Sewer availability Cleared 1/31/2025 DARIN LAM
Grading Pre-Inspection Cleared 1/31/2025 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 2/3/2025 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Zangoli,, Fabio; Lic. No.: NA6191       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 5/1/2025 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 5/12/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/3/2025 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/30/2025 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 7/14/2025 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 9/2/2025 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 9/4/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 9/4/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 9/4/2025 Approved DANIEL VERA
PLUMBING-Rough 9/4/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 9/9/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 9/9/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Approved CARLOS MATAMOROS
Deputy Steel/Welding 9/16/2025 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 9/18/2025 Partial Approval CARLOS MATAMOROS
Drywall Nailing 9/18/2025 Approved CARLOS MATAMOROS
Green Building Rough 9/18/2025 Approved CARLOS MATAMOROS
Insulation 9/18/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/23/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/7/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/23/2025 Approved CARLOS MATAMOROS
Shower Pan 10/23/2025 Approved CARLOS MATAMOROS
HVAC-Final 12/9/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/19/2025 Corrections Issued EVAN COOPER
PLUMBING-Final 12/19/2025 Approved EVAN COOPER
Final 12/20/2025 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/20/2025 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 12/20/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 1/7/2026 Approved EVAN COOPER
Final 1/7/2026 Permit Finaled EVAN COOPER
Smoke Detectors 1/7/2026 Approved EVAN COOPER