12105 W WATERFRONT DR Level 4 90094

Certificate Information: 12105 W WATERFRONT DR Level 4 90094

Application / Permit
24016-10000-38602
Plan Check / Job No.
B24LA34925
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan. Tenant Improvement at existing Office.
Permit Issued
Issued on 3/3/2025
Issuing Office
Current Status
Permit Finaled on 6/16/2025

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Zoning Architect 12/12/2024 BENNY WONG
Assigned to Plan Check Engineer 12/12/2024 PRANITA SHAH
Corrections Issued 12/19/2024 PRANITA SHAH
Quality Review Completed 1/2/2025 HERNAN ARREOLA
Applicant returned to address corrections 1/21/2025 PRANITA SHAH
Plan Check Approved 2/26/2025 PRANITA SHAH
Issued 3/3/2025 APPLICANT
Permit Finaled 6/13/2025 VASIL MIHALEV

Permit Application Clearance Information

DAS Clearance Cleared 12/19/2024 Aung Soe
Green Code Cleared 1/3/2025 Aung Soe
Specific Plan Cleared 1/3/2025 CAELAN RAFFERTY
Zoning Plan Check Cleared 2/12/2025 BENNY WONG

Contact Information

Architect Daly,, Kevin Michael; Lic. No.: NA19005       ,
Contractor Swinerton Builders; Lic. No.: 92-B       ,
Engineer Wilkerson,, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 4/1/2025 Approved VASIL MIHALEV
Drywall Nailing 4/4/2025 Approved VASIL MIHALEV
Insulation 4/4/2025 Approved VASIL MIHALEV
Drywall Nailing 4/14/2025 Approved VASIL MIHALEV
Drywall Nailing 4/23/2025 Not Ready for Inspection VASIL MIHALEV
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Approved VASIL MIHALEV
Insulation 5/2/2025 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 5/2/2025 Partial Approval RICARDO ROBLES
Drywall Nailing 5/6/2025 Approved VASIL MIHALEV
Light Gage Steel Frame 5/6/2025 Approved VASIL MIHALEV
Light Gage Steel Frame 5/12/2025 Approved VASIL MIHALEV
Light Gage Steel Frame 5/21/2025 Approved VASIL MIHALEV
T-Bar Ceiling 5/21/2025 Approved VASIL MIHALEV
Final 6/10/2025 Not Ready for Inspection VASIL MIHALEV
Green Building Final 6/10/2025 Approved VASIL MIHALEV
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Not Required VASIL MIHALEV
Smoke Detectors 6/10/2025 Approved VASIL MIHALEV
Final 6/13/2025 Permit Finaled VASIL MIHALEV