12250 W GORHAM AVE 90049

Certificate Information: 12250 W GORHAM AVE 90049

Application / Permit
24016-10000-38477
Plan Check / Job No.
B24LA34766
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan convert (e) detached 1-story garage resulting in a detached ADU w/ an attached carport per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/11/2025
Issuing Office
Current Status
CofO in Progress on 10/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/5/2024 APPLICANT
Assigned to Plan Check Engineer 12/9/2024 KELVIN CHUONG
Corrections Issued 12/10/2024 KELVIN CHUONG
Applicant returned to address corrections 2/5/2025 SUNMIN LEE
Plan Check Approved 2/10/2025 SUNMIN LEE
Issued 2/11/2025 APPLICANT
CofO in Progress 10/3/2025 ARAM AVEDISIAN

Permit Application Clearance Information

Specific Plan Cleared 12/13/2024 PEDRO AYALA
Address approval Cleared 12/17/2024 DIANA RENTERIA
Sewer availability Cleared 12/17/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 1/29/2025 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 16905 ARMDORE AVE      BELLFLOWER, CA 90706

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/9/2025 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 6/9/2025 Conditional Approval KIRK SANDERS
Underground Mechanical 6/9/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 6/20/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 6/20/2025 Corrections Issued KIRK SANDERS
Green Building Rough 6/20/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 6/20/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 6/20/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 6/20/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 6/27/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 6/27/2025 Approved KIRK SANDERS
HVAC-Rough 6/27/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 6/27/2025 Approved KIRK SANDERS
Underground Mechanical 6/27/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/30/2025 Corrections Issued KIRK SANDERS
Green Building Rough 6/30/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 6/30/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/8/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 7/8/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 7/16/2025 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 7/16/2025 Corrections Issued HAMIK HARTOUNIAN
Insulation 7/18/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 7/23/2025 Approved ARAM AVEDISIAN
Shower Pan 7/24/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/28/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 9/23/2025 Approved ARAM AVEDISIAN
HVAC-Final 9/23/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 9/23/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Final 9/25/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Final 9/25/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/3/2025 Approved ARAM AVEDISIAN
Final 10/3/2025 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 10/3/2025 Approved ARAM AVEDISIAN
Green Building Rough 10/3/2025 Approved ARAM AVEDISIAN
HVAC-Final 10/3/2025 Approved ARAM AVEDISIAN
Smoke Detectors 10/3/2025 Approved ARAM AVEDISIAN