1443 W JEFFERSON BLVD 90007
Certificate Information: 1443 W JEFFERSON BLVD 90007
- Application / Permit
- 24016-10000-38240
- Plan Check / Job No.
- B24LA34421
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Art Gallery
- Work Description
- [ePlan] Interion TI to existing Art Gallery. No change of occupant load.
- Permit Issued
- Issued on 5/5/2025
- Issuing Office
- Current Status
- Permit Finaled on 2/11/2026
Permit Application Status History
| Submitted | 12/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 12/5/2024 | FRANCIS AHN |
| Corrections Issued | 12/7/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 12/9/2024 | PETER KIM |
| Applicant returned to address corrections | 4/8/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/10/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/14/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/21/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/28/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 5/5/2025 | SALVADOR QUINTANILLA |
| Issued | 5/5/2025 | APPLICANT |
| Permit Finaled | 1/21/2026 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/18/2025 | DAVID LOPEZ |
| DAS Clearance | Cleared | 4/17/2025 | Joseph Rafols |
| Zoning Plan Check | Cleared | 5/2/2025 | Joseph Rafols |
Contact Information
| Contractor | Socal First Cornerstone Construction; Lic. No.: 1025857-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 8/22/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 9/3/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 9/9/2025 | Approved | ALFREDO LOPEZ |
| Final | 11/24/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 11/24/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 1/15/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 1/15/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 1/21/2026 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 1/21/2026 | Approved | ALFREDO LOPEZ |