809 N BRAMBLE WAY 90049
Certificate Information: 809 N BRAMBLE WAY 90049
- Application / Permit
- 24016-10000-38222
- Plan Check / Job No.
- B24LA34409
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND NEW ADDITION TO (E) 1-STORY SINGLE-FAMILY DWELLING TO HAVE A 1-STORY SFD OVER BASEMEN -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 9/10/2025
- Issuing Office
- Metro
- Current Status
- Issued on 9/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/12/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/17/2024 | KEN GILL |
| Building Plans Picked Up | 12/18/2024 | APPLICANT |
| Applicant returned to address corrections | 3/28/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 8/19/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/27/2025 | MAHNAZ NOURHASHEMI |
| Issued | 9/10/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/19/2024 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 12/19/2024 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 12/19/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2024 | ANTHONY MAINEZ |
| Permit | Cleared | 12/19/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/19/2024 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 1/7/2025 | MIGUEL ORNELAS |
| Construction near power lines | Cleared | 1/8/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/8/2025 | RIDWAN HARDY |
| ZA Case | Cleared | 1/8/2025 | JAZMIN ROQUE |
| BHO/Hillside ordinance | Cleared | 1/10/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 1/10/2025 | KIMBERLY HERNANDEZ |
| Hydrant and Access approval | Cleared | 1/16/2025 | PATRICK PEREZ |
| GPI Written Notices | Cleared | 3/28/2025 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 3/28/2025 | MAHNAZ NOURHASHEMI |
| Low Impact Development (LID) | Cleared | 4/10/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/10/2025 | LIAM ODONOVAN |
| Excavation more than 5-ft deep | Cleared | 8/5/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | Luxe Development Inc; Lic. No.: 993473-B | 314 ABINGTON DR BEVERLY HILLS, CA 90210 |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
| Engineer | Kile,, Johnny C; Lic. No.: C92658 | 3627 W 64TH STREET LOS ANGELES, CA 90043 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| No Data Available. |
Pending Inspections
| Footing/Foundation/Slab | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 10/20/2025 | Partial Inspection | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 12/16/2025 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Other (see comments) | 12/19/2025 | Conditional Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 2/5/2026 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/3/2026 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/30/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/5/2026 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/14/2026 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 5/20/2026 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/21/2026 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 5/22/2026 | Conditional Approval | ANDREW NAVE |