8363 S CHASE AVE 90045
Certificate Information: 8363 S CHASE AVE 90045
- Application / Permit
- 24016-10000-37997
- Plan Check / Job No.
- B24LA34076
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20' 1" X 20' 1" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- Issued on 2/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 12/5/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 1/10/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/8/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/24/2025 | GURUNATH NESARAJAH |
| Issued | 2/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 12/14/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2024 | LIAM ODONOVAN |
| Construction near power lines | Cleared | 2/4/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/1/2025 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 6/4/2025 | Conditional Approval | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 6/5/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 6/18/2025 | Approved | RUBEN RIVAS |
| Insulation | 6/18/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 6/26/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 6/26/2025 | Approved | JAYLIN GRAVITTE |
| Final | 11/10/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Green Building Final | 11/10/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Smoke Detectors | 11/10/2025 | Partial Approval | RUBEN RIVAS |
| Wood Frame | 11/10/2025 | Approved | RUBEN RIVAS |
| Final | 11/17/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 11/17/2025 | Approved | JESUS PINEDA |
| Final | 11/25/2025 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Ready | JESUS PINEDA |
| Final | 12/5/2025 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | JESUS PINEDA |