3229 W CASITAS AVE 90039
Certificate Information: 3229 W CASITAS AVE 90039
- Application / Permit
- 24016-10000-37946
- Plan Check / Job No.
- B24LA33968
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ePlan. Change a portion of the building from existing sound score production to restaurant. No change in building footprint.
- Permit Issued
- Issued on 9/24/2025
- Issuing Office
- Current Status
- Issued on 9/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Zoning Architect | 12/5/2024 | MEGAN KOLP |
| Assigned to Plan Check Engineer | 12/12/2024 | SAM CHANG |
| Corrections Issued | 12/20/2024 | TU HUA |
| Quality Review Completed | 12/24/2024 | CHAD DOI |
| Applicant returned to address corrections | 2/28/2025 | SAM CHANG |
| Applicant returned to address corrections | 8/6/2025 | TU HUA |
| Plan Check Approved | 9/17/2025 | TU HUA |
| Issued | 9/24/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 2/18/2025 | DORIAN AGUILAR |
| ZA Case | Cleared | 2/18/2025 | DORIAN AGUILAR |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2025 | DAVID VO |
| Sewer availability | Cleared | 2/27/2025 | DAVID VO |
| Fire Marshal Fire Life Safety | Cleared | 3/22/2025 | MENOA AGHAJANI |
| Food Service Establishment | Cleared | 5/15/2025 | STANLEY WING |
| ZA Case | Cleared | 5/30/2025 | MATTHEW COMPANA |
| DAS Clearance | Cleared | 6/12/2025 | Shangqin Xie |
| Food establishment approval | Cleared | 7/8/2025 | LACDHS APPROVED |
| Zoning Plan Check | Cleared | 7/25/2025 | MEGAN KOLP |
Contact Information
| Contractor | Jk Builder Incorporation; Lic. No.: 1128191-B | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/4/2025 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 12/4/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 12/4/2025 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 12/4/2025 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 12/4/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 2/6/2026 | Approved | RAFAEL CORTES |
| T-Bar Ceiling | 2/6/2026 | Not Ready for Inspection | RAFAEL CORTES |