6333 W 3RD ST 706 90036
Certificate Information: 6333 W 3RD ST 706 90036
- Application / Permit
- 24016-10000-37798
- Plan Check / Job No.
- B24LA33877
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- New tenant improvement to existing 2,486 sf restaurant. Increase patio from 691 sf to 1,070 sf. Project total 3,556 sf. Expedited Plan Check. Submitted for Restaurant Hospitality Program already.
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- CofO Issued on 5/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 12/5/2024 | SALVADOR QUINTANILLA |
| Corrections Issued | 12/7/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 12/9/2024 | PETER KIM |
| Applicant returned to address corrections | 12/16/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/3/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/8/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/13/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/19/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/20/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/11/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 5/6/2025 | SALVADOR QUINTANILLA |
| Issued | 5/7/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | MARTIN TAVITIAN |
| Permit Finaled | 5/18/2026 | RAFAEL ESPINOZA |
| CofO Issued | 5/18/2026 | RAFAEL ESPINOZA |
| Permit Finaled | 5/18/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 12/16/2024 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 12/16/2024 | LAMBERT GIESSINGER |
| ZA Case | Cleared | 12/24/2024 | RICARDO MARTINEZ |
| Roof/Waste drainage to street | Cleared | 12/31/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 12/31/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | TREVOR QUAN |
| Fire Marshal Fire Life Safety | Cleared | 3/14/2025 | WILLIAM JOHNS |
| Abandoned oil well | Cleared | 3/19/2025 | RUEL COLE |
| Green Code | Cleared | 3/21/2025 | Mohammad Esmaili |
| Food Service Establishment | Cleared | 3/25/2025 | KENNETH BROWNE |
| DAS Clearance | Cleared | 4/3/2025 | Mohammad Esmaili |
| Food establishment approval | Cleared | 4/11/2025 | LACDHS APPROVED |
| Zoning Plan Check | Cleared | 4/11/2025 | Mohammad Esmaili |
Contact Information
| Contractor | Terra Nova Industries; Lic. No.: 460854-B | , |
| Engineer | Murphy,, Michael Nicholas; Lic. No.: C71600 | 935 W 19TH ST SANTA ANA, CA 92706 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 6/5/2025 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 6/11/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Barrier | 7/9/2025 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 7/14/2025 | Partial Approval | MARTIN TAVITIAN |
| METHANE-Subgrade | 7/14/2025 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 7/23/2025 | Partial Approval | MARTIN TAVITIAN |
| Green Building Rough | 9/29/2025 | Approved | MARTIN TAVITIAN |
| Light Gage Steel Frame | 9/29/2025 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 9/29/2025 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 9/30/2025 | Approved | MARTIN TAVITIAN |
| Insulation | 10/1/2025 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 10/7/2025 | Approved | MARTIN TAVITIAN |
| Light Gage Steel Frame | 10/21/2025 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 10/21/2025 | Partial Approval | MARTIN TAVITIAN |
| Drywall Nailing | 10/31/2025 | Approved | MARTIN TAVITIAN |
| Smoke Detectors | 10/31/2025 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 11/3/2025 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 11/4/2025 | Approved | MARTIN TAVITIAN |
| Final | 1/8/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 1/8/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | MARTIN TAVITIAN |
| Wood Frame | 1/8/2026 | Conditional Approval | MARTIN TAVITIAN |
| Pre-Inspection | 1/12/2026 | Approved | MARTIN TAVITIAN |
| Final | 2/9/2026 | OK to Issue CofO | MARTIN TAVITIAN |
| Green Building Final | 2/9/2026 | Approved | MARTIN TAVITIAN |
| Wood Frame | 2/9/2026 | Approved | MARTIN TAVITIAN |