300 S GRAND AVE 2500 90071

Certificate Information: 300 S GRAND AVE 2500 90071

Application / Permit
24016-10000-37597
Plan Check / Job No.
B24LA33545
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan TENANT IMPROVEMENT IN SUITE 2500 OF SPRINKLERED OFFICE BUILDING NEW NON- STRUCTURAL AND NON-RATED PARTITIONS FOR NEW OFFICES, NEW LIGHTING THROUGHOUT, MINOR ELECTRICAL, CEILING WORK AND FINISHES IN SPECIFIED AREAS. MINOR DEMOLITION OF NON-LOAD BEARING WALL AT EXISTING ROOM.
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
Permit Finaled on 8/4/2025

Permit Application Status History

Submitted 11/26/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 FARSHAD ALIMOHAMADI
Corrections Issued 11/27/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/21/2025 ADAM HEGAZI
Plan Check Approved 2/6/2025 ADAM HEGAZI
Issued 3/27/2025 APPLICANT
Permit Finaled 8/4/2025 PAUL BAZERKANIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Kerwin,, Jason Douglas; Lic. No.: NA29140       ,
Contractor Hitt Contracting Inc; Lic. No.: 811478-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 5/14/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 5/19/2025 Partial Approval LUIS CCAMACHO
Insulation 5/22/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 5/27/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 6/5/2025 Partial Approval PAUL BAZERKANIAN
Final 8/4/2025 Permit Finaled PAUL BAZERKANIAN
Green Building Final 8/4/2025 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 8/4/2025 Approved PAUL BAZERKANIAN