1632 W 221ST ST 90501

Certificate Information: 1632 W 221ST ST 90501

Application / Permit
24016-10000-37525
Plan Check / Job No.
B24LA33487
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan -REMODEL ON 1ST FLOOR IN EXISTING 2 STORY SFD, NO CHANGES TO 2ND FLOOR
Permit Issued
Issued on 1/30/2025
Issuing Office
Current Status
Permit Finaled on 4/2/2026

Permit Application Status History

Submitted 11/26/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 STARR CHEN
Corrections Issued 12/2/2024 STARR CHEN
Quality Review Completed 12/4/2024 EUGENE BARBEAU
Applicant returned to address corrections 1/16/2025 STARR CHEN
Plan Check Approved 1/29/2025 STARR CHEN
Issued 1/30/2025 APPLICANT
Permit Finaled 4/2/2026 EUGENE CASSIDY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2025 XOCHITL ARQUIETA
Sewer availability Cleared 1/10/2025 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/3/2025 Approved EUGENE CASSIDY
Special/Order Compliance 4/3/2025 Corrections Issued EUGENE CASSIDY
Wood Frame 4/9/2025 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 4/16/2025 Partial Approval EUGENE CASSIDY
Wood Frame 4/28/2025 Corrections Issued EUGENE CASSIDY
Wood Frame 5/13/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 6/9/2025 Corrections Issued EUGENE CASSIDY
HVAC-Rough 6/9/2025 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 6/9/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/2/2025 Approved JOHN KLARIN
HVAC-Rough 7/2/2025 Corrections Issued JOHN KLARIN
PLUMBING-Rough 7/2/2025 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 7/3/2025 Approved JOHN KLARIN
HVAC-Rough 7/3/2025 Approved JOHN KLARIN
PLUMBING-Rough 7/3/2025 Approved JOHN KLARIN
Insulation 7/25/2025 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 7/25/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/7/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Approved EUGENE CASSIDY
Insulation 8/7/2025 Approved EUGENE CASSIDY
Drywall Nailing 9/5/2025 Approved EUGENE CASSIDY
Shower Pan 10/2/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/14/2025 Approved EUGENE CASSIDY
Final 3/10/2026 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 3/10/2026 Approved EUGENE CASSIDY
Final 3/19/2026 Corrections Issued EUGENE CASSIDY
Final 4/2/2026 Permit Finaled EUGENE CASSIDY