4023 S BEETHOVEN ST 90066

Certificate Information: 4023 S BEETHOVEN ST 90066

Application / Permit
24016-10000-37520
Plan Check / Job No.
B24LA33466
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert the existing detached garage into a new Accessory Dwelling Unit per state law
Permit Issued
Issued on 2/24/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2024 APPLICANT
Assigned to Plan Check Engineer 12/16/2024 SHANGQIN XIE
Corrections Issued 12/17/2024 SHANGQIN XIE
Applicant returned to address corrections 2/15/2025 NEHEMIAS RAMOS
Plan Check Approved 2/19/2025 NEHEMIAS RAMOS
Issued 2/24/2025 APPLICANT
CofO in Progress 2/27/2026 DAVID FEILER
Permit Finaled 3/3/2026 RICHARD STEINBACH
CofO Issued 3/3/2026 RICHARD STEINBACH
Permit Finaled 3/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/29/2024 LIAM ODONOVAN
Sewer availability Cleared 12/29/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 1/2/2025 LIAM ODONOVAN
Specific Plan Cleared 1/10/2025 PEDRO AYALA
Construction near power lines Cleared 2/10/2025 RIDWAN HARDY

Contact Information

Contractor Maestro Construction Inc; Lic. No.: 1060987-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/21/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 4/29/2025 Corrections Issued MICHAEL ALLEN
Deputy Drilled-In Anchors 5/23/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 5/28/2025 Partial Approval MICHAEL ALLEN
Deputy Drilled-In Anchors 6/17/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 6/20/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 7/11/2025 Approved WILBER ROSALES
Underground Mechanical 7/11/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 8/6/2025 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Rough 8/6/2025 Corrections Issued WILBER ROSALES
Green Building Rough 8/6/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Rough 8/6/2025 Approved WILBER ROSALES
PLUMBING-Rough 8/6/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 8/11/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/13/2025 Approved WILBER ROSALES
Green Building Rough 8/13/2025 Approved WILBER ROSALES
Sewer 8/13/2025 Approved WILBER ROSALES
Insulation 8/15/2025 Approved JAYLIN GRAVITTE
Insulation 8/19/2025 Approved JAYLIN GRAVITTE
Shower Pan 8/19/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 8/27/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 8/27/2025 Approved WILBER ROSALES
Final 2/20/2026 Corrections Issued DAKOTA LOW
Green Building Final 2/20/2026 Approved DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Not Required DAKOTA LOW
Smoke Detectors 2/20/2026 Approved DAKOTA LOW
ELECTRICAL-Final 2/24/2026 Approved ANTHONY EGSON
HVAC-Final 2/24/2026 Corrections Issued ANTHONY EGSON
PLUMBING-Final 2/24/2026 Corrections Issued ANTHONY EGSON
Final 2/27/2026 OK to Issue CofO DAVID FEILER
HVAC-Final 2/27/2026 Approved DAVID FEILER
PLUMBING-Final 2/27/2026 Approved DAVID FEILER