2640 W WAVERLY DR 90039

Certificate Information: 2640 W WAVERLY DR 90039

Application / Permit
24016-10000-37496
Plan Check / Job No.
B24LA33435
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
E-plan. Convert existing Duplex to Single Family Dwelling per Engineer Provide new interior staircase, Interior remodel, no sqft added
Permit Issued
Issued on 4/28/2025
Issuing Office
Current Status
Issued on 4/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 MAHNAZ NOURHASHEMI
Corrections Issued 12/9/2024 KHUONG TRUONG
Quality Review Completed 12/10/2024 PRANITA SHAH
Applicant returned to address corrections 1/9/2025 KHUONG TRUONG
Plan Check Approved 4/25/2025 MAHNAZ NOURHASHEMI
Issued 4/28/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/11/2025 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/12/2025 ADRIAN SANCHEZ
Sewer availability Cleared 1/17/2025 ADRIAN SANCHEZ
Demo/Removal of Rental Units Cleared 4/4/2025 DIEGO ROCHA
Tenant Habitability Plan Cleared 4/17/2025 KORNEL LELEA
Grading Pre-Inspection Cleared 4/18/2025 RUSSELL BONVOULOIR

Contact Information

Contractor The K & L Corporation; Lic. No.: 1119795-B       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/8/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 8/8/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/15/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 8/15/2025 Not Required HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/4/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/4/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/4/2025 Approved HAMIK HARTOUNIAN
MERV13>=Rough 9/4/2025 Approved HAMIK HARTOUNIAN
Special/Order Compliance 9/4/2025 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 9/10/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/10/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 9/10/2025 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/16/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 10/16/2025 Not Ready for Inspection GEM DE OCAMPO
Interior/Exterior Lathing 10/21/2025 Approved DEVON JACKSON
Final 1/29/2026 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 1/29/2026 Corrections Issued HAMIK HARTOUNIAN