1228 W 1ST ST 90732

Certificate Information: 1228 W 1ST ST 90732

Application / Permit
24016-10000-37398
Plan Check / Job No.
B24LA33300
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING DETACHED 1-CAR GARAGE TO BE CONVERTED TO NEW ADU (227 SQFT) PER STATE LAW. "COMPLY WITH DEPARTMENT ORDER effective date 10/24/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/27/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 LUKE GONZALES
Corrections Issued 11/30/2024 LUKE GONZALES
Building Plans Picked Up 12/4/2024 APPLICANT
Plan Check Approved 12/27/2024 DANIEL SMILEY
Issued 12/27/2024 APPLICANT
CofO in Progress 8/4/2025 PAUL REECE
Permit Finaled 4/16/2026 CLAUDIO MORENO
CofO Issued 4/16/2026 CLAUDIO MORENO
Permit Finaled 4/16/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 12/20/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 12/20/2024 AMBER CAMPBELL
Sewer availability Cleared 12/20/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/25/2025 Corrections Issued PAUL REECE
Pre-Inspection 3/25/2025 Approved PAUL REECE
Footing/Foundation/Slab 4/8/2025 Corrections Issued PAUL REECE
Deputy Drilled-In Anchors 4/14/2025 Approved PAUL REECE
Footing/Foundation/Slab 4/17/2025 Approved PAUL REECE
Wood Frame 4/24/2025 Approved PAUL REECE
Deputy Wood Construction 4/29/2025 Approved PAUL REECE
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Approved PAUL REECE
Insulation 4/29/2025 Approved PAUL REECE
Deputy Methane Barrier 6/3/2025 Approved PAUL REECE
Drywall Nailing 6/3/2025 Approved PAUL REECE
ELECTRICAL-Rough 6/3/2025 Corrections Issued PAUL REECE
HVAC-Rough 6/3/2025 Partial Approval PAUL REECE
PLUMBING-Rough 6/3/2025 Approved PAUL REECE
ELECTRICAL-Final 6/25/2025 Partial Approval PAUL REECE
Service/Power Release 6/25/2025 Approved PAUL REECE
PLUMBING-Final 7/10/2025 Not Ready for Inspection PAUL REECE
Sewer 7/11/2025 Approved PAUL REECE
BUILDING-Rough-Frame 7/24/2025 Approved PAUL REECE
Final 7/24/2025 Conditional Approval PAUL REECE
Green Building Final 7/24/2025 Approved PAUL REECE
Green Building Rough 7/24/2025 Approved PAUL REECE
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Not Required PAUL REECE
Smoke Detectors 7/24/2025 Approved PAUL REECE
Final 8/4/2025 OK to Issue CofO PAUL REECE