1855 S BUCKINGHAM ROAD 90019

Certificate Information: 1855 S BUCKINGHAM ROAD 90019

Application / Permit
24016-10000-37317
Plan Check / Job No.
B24LA33199
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert existing detached Garage to ADU & Storage per engineer design (Conversion of Accessory Building per State Law , CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 1/22/2025
Issuing Office
Current Status
CofO Issued on 12/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/2/2024 JOSE VELAZQUEZ
Corrections Issued 12/3/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 1/17/2025 AUNG SOE
Plan Check Approved 1/20/2025 AUNG SOE
Issued 1/22/2025 APPLICANT
CofO in Progress 12/19/2025 JUSTIN HAWLEY
Permit Finaled 12/20/2025 DEROLD HAUFF
CofO Issued 12/20/2025 DEROLD HAUFF
Permit Finaled 12/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/11/2024 CHRISTINA BRACO
Sewer availability Cleared 12/11/2024 CHRISTINA BRACO
CPC Cleared 12/23/2024 LAMBERT GIESSINGER
HPOZ Cleared 12/23/2024 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 12/23/2024 LAMBERT GIESSINGER
Eng Process Fee Ord 176,300 Cleared 12/26/2024 CHRISTINA BRACO

Contact Information

Contractor Sulgatti General Contractors Inc; Lic. No.: 912572-B       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/6/2025 Conditional Approval JEFFREY MEAD
Pre-Inspection 3/12/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/12/2025 Partial Inspection ALEX COLIN
Footing/Foundation/Slab 3/17/2025 Partial Approval RONNIE MINDANAO
Deputy Drilled-In Anchors 3/26/2025 Conditional Approval JEFFREY MEAD
Footing/Foundation/Slab 4/1/2025 Approved LUIS CASTRO
PLUMBING-Rough 4/1/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 5/23/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 5/23/2025 Corrections Issued RONNIE MINDANAO
HVAC-Rough 5/23/2025 Corrections Issued RONNIE MINDANAO
METHANE-Rough 5/23/2025 Approved RONNIE MINDANAO
PLUMBING-Rough 5/23/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Approved ENRIQUE MIRELES
HVAC-Rough 5/28/2025 Approved ENRIQUE MIRELES
Wood Frame 5/28/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 6/3/2025 Approved JUSTIN HAWLEY
Insulation 6/3/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 6/3/2025 Approved JUSTIN HAWLEY
Special/Order Compliance 6/3/2025 Corrections Issued JUSTIN HAWLEY
Drywall Nailing 6/11/2025 Approved JUSTIN HAWLEY
Green Building Rough 6/11/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/11/2025 Partial Approval JUSTIN HAWLEY
Sewer 6/17/2025 Approved JUSTIN HAWLEY
Underground Mechanical 6/17/2025 Approved JUSTIN HAWLEY
Shower Pan 6/25/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 6/27/2025 Approved ALEX COLIN
Final 11/26/2025 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 11/26/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Final 12/19/2025 Approved JUSTIN HAWLEY
Final 12/19/2025 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 12/19/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 12/19/2025 Approved JUSTIN HAWLEY