1855 S BUCKINGHAM ROAD 90019
Certificate Information: 1855 S BUCKINGHAM ROAD 90019
- Application / Permit
- 24016-10000-37317
- Plan Check / Job No.
- B24LA33199
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert existing detached Garage to ADU & Storage per engineer design (Conversion of Accessory Building per State Law , CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Current Status
- CofO Issued on 12/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 12/3/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 1/17/2025 | AUNG SOE |
| Plan Check Approved | 1/20/2025 | AUNG SOE |
| Issued | 1/22/2025 | APPLICANT |
| CofO in Progress | 12/19/2025 | JUSTIN HAWLEY |
| Permit Finaled | 12/20/2025 | DEROLD HAUFF |
| CofO Issued | 12/20/2025 | DEROLD HAUFF |
| Permit Finaled | 12/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 12/11/2024 | CHRISTINA BRACO |
| CPC | Cleared | 12/23/2024 | LAMBERT GIESSINGER |
| HPOZ | Cleared | 12/23/2024 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 12/23/2024 | LAMBERT GIESSINGER |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Sulgatti General Contractors Inc; Lic. No.: 912572-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/6/2025 | Conditional Approval | JEFFREY MEAD |
| Pre-Inspection | 3/12/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/12/2025 | Partial Inspection | ALEX COLIN |
| Footing/Foundation/Slab | 3/17/2025 | Partial Approval | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 3/26/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/1/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 4/1/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 5/23/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 5/23/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 5/23/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 5/23/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/28/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 5/28/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/3/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 6/3/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 6/3/2025 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 6/3/2025 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 6/11/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 6/11/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/11/2025 | Partial Approval | JUSTIN HAWLEY |
| Sewer | 6/17/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 6/17/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 6/25/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/27/2025 | Approved | ALEX COLIN |
| Final | 11/26/2025 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 11/26/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 12/19/2025 | Approved | JUSTIN HAWLEY |
| Final | 12/19/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 12/19/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 12/19/2025 | Approved | JUSTIN HAWLEY |