12202 W VENTURA BLVD 91604

Certificate Information: 12202 W VENTURA BLVD 91604

Application / Permit
24016-10000-37297
Plan Check / Job No.
B24LA33175
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Tenant improvement to combine (2) retail spaces to make them one (1) tenant space for retail sales (Ariat). Work to include demolition of previous tenant construction, new exterior storefront, new non-structural partitions, finishes, flooring, furniture and equipment, and shelving.
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
Permit Finaled on 6/24/2025

Permit Application Status History

Submitted 11/22/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 JOE VO
Corrections Issued 11/30/2024 JOE VO
Quality Review Completed 12/3/2024 PRANITA SHAH
Assigned to Zoning Architect 12/5/2024 LY CHEA
Plan Check Approved 4/16/2025 JOE VO
Issued 4/16/2025 APPLICANT
Permit Finaled 6/24/2025 DANIEL VARNUM

Permit Application Clearance Information

Specific Plan Cleared 12/24/2024 ADRINEH MELKONIAN
Specific Plan Cleared 1/24/2025 ALBERT ISAGULIAN
Green Code Cleared 2/4/2025 MICHAEL AYERS
DAS Clearance Cleared 4/1/2025 Angelica Martinez
Zoning Plan Check Cleared 4/4/2025 Angelica Martinez

Contact Information

Architect Wakeman,, Steven Bruce; Lic. No.: C34662 701 UNIVERSITY AVE #210      SACRAMENTO, CA 95825
Contractor Lakeview Construction Inc; Lic. No.: 671201-B       ,
Contractor Lakeview Construction Llc; Lic. No.: 671201-B       ,
Engineer Young,, Bradley Rae; Lic. No.: S4727 345 POLLASKY AVENUE      CLOVIS, CA 93612

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 4/18/2025 Conditional Approval DEANDRE HOFFMAN
Drywall Nailing 4/24/2025 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 4/25/2025 Partial Approval JOHN KITCKO
Deputy Steel/Welding 5/8/2025 Conditional Approval KENNETH ROBERTS
Deputy Drilled-In Anchors 5/12/2025 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 5/12/2025 Approved KENNETH ROBERTS
Light Gage Steel Frame 5/22/2025 Partial Approval KENNETH ROBERTS
Light Gage Steel Frame 5/28/2025 Approved DEANDRE HOFFMAN
Drywall Nailing 5/30/2025 Partial Approval ROBERT DAVIS
T-Bar Ceiling 6/4/2025 Conditional Approval DANIEL VARNUM
Final 6/18/2025 Partial Approval DANIEL VARNUM
Green Building Final 6/18/2025 Approved DANIEL VARNUM
Green Building Rough 6/18/2025 Approved DANIEL VARNUM
Reinforced Masonry Frame 6/18/2025 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV No Gas DANIEL VARNUM
Smoke Detectors 6/18/2025 Approved DANIEL VARNUM
Final 6/24/2025 Permit Finaled DANIEL VARNUM