5379-5379 1/2 E SOMERSET ST 90032
Certificate Information: 5379-5379 1/2 E SOMERSET ST 90032
- Application / Permit
- 24016-10000-37246
- Plan Check / Job No.
- B24LA33106
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF SINGLE FAMILY DWELLING (312 SF) TO NEW JADU PER STATE LAW
- Permit Issued
- Issued on 4/9/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2024 | ADAM HEGAZI |
| Corrections Issued | 11/27/2024 | ADAM HEGAZI |
| Building Plans Picked Up | 12/11/2024 | APPLICANT |
| Applicant returned to address corrections | 2/4/2025 | ZAW HAN |
| Applicant returned to address corrections | 3/21/2025 | SUNMIN LEE |
| Plan Check Approved | 4/8/2025 | NGHI SU |
| Issued | 4/9/2025 | APPLICANT |
| CofO in Progress | 2/3/2026 | LILIANA PORTILLO |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
| CofO Issued | 2/7/2026 | DEROLD HAUFF |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/21/2025 | ADAM HEGAZI |
| Address approval | Cleared | 3/26/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/26/2025 | DAVID LOPEZ |
Contact Information
| Architect | Aaron, Olko; Lic. No.: C39064 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/3/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/25/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/25/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 11/25/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/2/2025 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 12/2/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 12/2/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/2/2025 | Approved | LILIANA PORTILLO |
| Insulation | 12/3/2025 | Conditional Approval | LILIANA PORTILLO |
| Drywall Nailing | 12/8/2025 | Partial Approval | GEM DE OCAMPO |
| Interior/Exterior Lathing | 12/22/2025 | Not Ready for Inspection | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 1/7/2026 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/7/2026 | Approved | LILIANA PORTILLO |
| Insulation | 1/7/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/7/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/23/2026 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 1/23/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/26/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/27/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/27/2026 | Corrections Issued | LILIANA PORTILLO |
| Final | 2/2/2026 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 2/2/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 2/2/2026 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 2/2/2026 | Approved | LILIANA PORTILLO |