5377 E SOMERSET ST 90032

Certificate Information: 5377 E SOMERSET ST 90032

Application / Permit
24016-10000-37245
Plan Check / Job No.
B24LA33106
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND STORAGE TO NEW ADU PER STATE LAW.
Permit Issued
Issued on 4/9/2025
Issuing Office
Metro
Current Status
CofO Issued on 10/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/25/2024 ADAM HEGAZI
Corrections Issued 11/27/2024 ADAM HEGAZI
Building Plans Picked Up 12/11/2024 APPLICANT
Applicant returned to address corrections 2/4/2025 ZAW HAN
Applicant returned to address corrections 3/21/2025 SUNMIN LEE
Plan Check Approved 4/8/2025 NGHI SU
Issued 4/9/2025 APPLICANT
CofO in Progress 10/27/2025 LILIANA PORTILLO
Permit Finaled 10/27/2025 DEROLD HAUFF
CofO Issued 10/27/2025 DEROLD HAUFF
Permit Finaled 10/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/21/2025 ADAM HEGAZI
Address approval Cleared 3/26/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/26/2025 DAVID LOPEZ
Sewer availability Cleared 3/26/2025 DAVID LOPEZ

Contact Information

Architect Olko,, Aaron Ensign; Lic. No.: C39064    6542 OCEAN CREST DR. B206    RANCHO PALOS VERDES, CA 90275
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/8/2025 Corrections Issued LILIANA PORTILLO
Underground Mechanical 7/8/2025 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 7/14/2025 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/15/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 7/15/2025 Corrections Issued LILIANA PORTILLO
Sewer 7/15/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 8/12/2025 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 8/29/2025 Approved LILIANA PORTILLO
HVAC-Rough 8/29/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 8/29/2025 Corrections Issued LILIANA PORTILLO
Gas Test 9/3/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 9/3/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/8/2025 Corrections Issued LILIANA PORTILLO
Insulation 9/18/2025 Corrections Issued ANTHONY RAMOS
BUILDING-Rough-Frame 9/29/2025 Approved LILIANA PORTILLO
Insulation 9/29/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/29/2025 Approved LILIANA PORTILLO
Drywall Nailing 10/1/2025 Approved LILIANA PORTILLO
Underground Mechanical 10/3/2025 Partial Approval LILIANA PORTILLO
HVAC-Final 10/21/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 10/21/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 10/23/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 10/23/2025 Approved LILIANA PORTILLO
PLUMBING-Final 10/23/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Not Ready LILIANA PORTILLO
Underground Mechanical 10/23/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/24/2025 Approved LILIANA PORTILLO
Final 10/24/2025 OK to Issue CofO LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 10/24/2025 Approved LILIANA PORTILLO