704 1/2 W GAGE AVE 90044

Certificate Information: 704 1/2 W GAGE AVE 90044

Application / Permit
24016-10000-37180
Plan Check / Job No.
B24LA32974
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED 3-CAR GARAGE INTO ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/23/2024
Issuing Office
Current Status
CofO Issued on 5/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 JOHNPAUL ISIP
Corrections Issued 12/2/2024 JOHNPAUL ISIP
Plan Check Approved 12/21/2024 REZA HAGHIGHAT
Issued 12/23/2024 APPLICANT
CofO in Progress 5/6/2025 BARRY HACHE
Permit Finaled 5/7/2025 DEROLD HAUFF
CofO Issued 5/7/2025 DEROLD HAUFF
Permit Finaled 5/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/12/2024 CHRISTINA BRACO
Sewer availability Cleared 12/12/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 12/13/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/22/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Approved BARRY HACHE
ELECTRICAL-Rough 2/18/2025 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 2/18/2025 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 2/21/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 2/21/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/26/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 2/26/2025 Not Ready for Inspection BARRY HACHE
Shower Pan 2/26/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 3/3/2025 Approved BARRY HACHE
Green Building Rough 3/3/2025 Approved BARRY HACHE
HVAC-Rough 3/3/2025 Approved BARRY HACHE
Shower Pan 3/3/2025 Approved BARRY HACHE
Insulation 3/7/2025 Approved WILLIAM SIERRA
Drywall Nailing 3/11/2025 Corrections Issued BARRY HACHE
Drywall Nailing 3/13/2025 Not Ready for Inspection ANTHONY RAMOS
Drywall Nailing 3/18/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 3/18/2025 Approved ANTHONY RAMOS
Service/Power Release 4/10/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 4/15/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 4/15/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 4/21/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 4/21/2025 Approved BARRY HACHE
ELECTRICAL-Final 4/29/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 4/29/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 5/2/2025 Approved BARRY HACHE
Final 5/6/2025 OK to Issue CofO BARRY HACHE
Green Building Final 5/6/2025 Approved BARRY HACHE
HVAC-Final 5/6/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved BARRY HACHE
Service/Power Release 5/6/2025 Approved BARRY HACHE
Smoke Detectors 5/6/2025 Approved BARRY HACHE