8227 W BLACKBURN AVE 90048

Certificate Information: 8227 W BLACKBURN AVE 90048

Application / Permit
24016-10000-37026
Plan Check / Job No.
B24LA32713
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Steel Moment Frame and new wood shear walls. ADU Conversion permit obtained under separate permit 22016-30000-17455 for parking stall conversion to ADU units. Certificate of Compliance for Soft Story Shall not be issued till Certificate of Occupancy for ADU is obtained.
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
Issued on 3/13/2025

Permit Application Status History

Submitted 11/20/2024 APPLICANT
Assigned to Plan Check Engineer 11/20/2024 VARAND SARKISIAN
Corrections Issued 11/25/2024 VARAND SARKISIAN
Quality Review Completed 12/11/2024 HANS SANTIAGO
Plan Check Approved 2/5/2025 VARAND SARKISIAN
Issued 3/13/2025 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 1/21/2025 KORNEL LELEA
Tenant Habitability Plan Cleared 1/21/2025 KORNEL LELEA

Contact Information

Architect Daham,, Ramsey Walid; Lic. No.: C34257 127 ARENA STREET      EL SEGUNDO, CA 90245
Contractor Chase Construction Inc; Lic. No.: 700816-B       ,
Contractor Supreme Construction; Lic. No.: 700816-B       ,
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 5/22/2025 Not Ready for Inspection DARRYL ARNOLD
Special/Order Compliance 6/6/2025 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 6/9/2025 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 6/16/2025 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 6/17/2025 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 6/25/2025 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/8/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 10/8/2025 Corrections Issued DARRYL ARNOLD
Deputy Reinf. Concrete 10/10/2025 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 11/4/2025 Corrections Issued DARRYL ARNOLD
Special/Order Compliance 11/5/2025 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 5/22/2026 Conditional Approval DARRYL ARNOLD