2221 S WESTERN AVE 103 90018
Certificate Information: 2221 S WESTERN AVE 103 90018
- Application / Permit
- 24016-10000-37010
- Plan Check / Job No.
- B24LA32697
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Initial T.I remodel @ suite 103. Non bearing interior partitions
- Permit Issued
- Issued on 12/20/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/29/2025
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 11/19/2024 | JOSEPH RAFOLS |
| Issued | 12/20/2024 | APPLICANT |
| Permit Finaled | 8/26/2025 | ALFREDO LOPEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 2/26/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Light Gage Steel Frame | 2/26/2025 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 3/20/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Light Gage Steel Frame | 3/20/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 3/21/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 3/24/2025 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 3/27/2025 | Approved | ALFREDO LOPEZ |
| Light Gage Steel Frame | 3/27/2025 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 4/4/2025 | Approved | ALFREDO LOPEZ |
| T-Bar Ceiling | 4/15/2025 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 5/23/2025 | Approved | ALFREDO LOPEZ |
| Final | 5/30/2025 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 5/30/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 6/3/2025 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 6/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Special/Order Compliance | 6/3/2025 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 7/30/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 8/26/2025 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 8/26/2025 | Approved | ALFREDO LOPEZ |