13063-13065 W ADDISON ST 91423

Certificate Information: 13063-13065 W ADDISON ST 91423

Application / Permit
24016-10000-36926
Plan Check / Job No.
B24LA32581
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert existing attached garage into JADU per CA Govt. Code 65852.2(e)(1)(A) and 65852.22. Design per licensed engineer.
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2024 APPLICANT
Assigned to Plan Check Engineer 11/22/2024 CAROLEAN BASMA
Corrections Issued 11/23/2024 CAROLEAN BASMA
Applicant returned to address corrections 2/26/2025 YASHAR EMAMI
Plan Check Approved 3/5/2025 YASHAR EMAMI
Issued 3/6/2025 APPLICANT
CofO in Progress 9/15/2025 OGANES TARAKHCHYAN
Permit Finaled 3/12/2026 RUBEN SALAS
Permit Finaled 3/12/2026 RUBEN SALAS
CofO Issued 3/12/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/26/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/26/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/2/2024 EDGAR ALCARAZ
ZA Case Cleared 12/4/2024 BRENNEN OBETO

Contact Information

Contractor Kdn Builders Group Inc; Lic. No.: 1120729-B       ,
Engineer Braun,, Jason; Lic. No.: C70948 14390 SHAWNEE ST      MOORPARK, CA 93021

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 3/19/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/25/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/25/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 3/25/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 3/25/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 4/1/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/1/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/2/2025 Partial Approval OGANES TARAKHCHYAN
Insulation 4/2/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/3/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 4/3/2025 Approved OGANES TARAKHCHYAN
Shower Pan 4/7/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/8/2025 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/21/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 6/4/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 6/4/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 6/4/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 6/4/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 6/4/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Not Required OGANES TARAKHCHYAN
Smoke Detectors 6/4/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 6/11/2025 Approved GAREN HAYRAPETYAN
Final 6/11/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 6/11/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 6/11/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 6/11/2025 Approved GAREN HAYRAPETYAN
Final 9/12/2025 OK to Issue CofO OGANES TARAKHCHYAN