13063-13065 W ADDISON ST 91423
Certificate Information: 13063-13065 W ADDISON ST 91423
- Application / Permit
- 24016-10000-36926
- Plan Check / Job No.
- B24LA32581
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing attached garage into JADU per CA Govt. Code 65852.2(e)(1)(A) and 65852.22. Design per licensed engineer.
- Permit Issued
- Issued on 3/6/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2024 | CAROLEAN BASMA |
| Corrections Issued | 11/23/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 2/26/2025 | YASHAR EMAMI |
| Plan Check Approved | 3/5/2025 | YASHAR EMAMI |
| Issued | 3/6/2025 | APPLICANT |
| CofO in Progress | 9/15/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
| CofO Issued | 3/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/26/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | EDGAR ALCARAZ |
| ZA Case | Cleared | 12/4/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Kdn Builders Group Inc; Lic. No.: 1120729-B | , |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/19/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 3/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/1/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/1/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/2/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/2/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/3/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/3/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/7/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/8/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/21/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 6/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 6/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 6/4/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Not Required | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/4/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/11/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 9/12/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |