2535 E 12TH ST Suite A 90023
Certificate Information: 2535 E 12TH ST Suite A 90023
- Application / Permit
- 24016-10000-36864
- Plan Check / Job No.
- B24LA32457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Photographer
- Work Description
- **ePlan** ** change of use from Warehouse to Photography Studio and Tenant Improvement. New interior non-load bearing partitions. Installation of (n) roof insulations.
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | JOHNNY WU |
| Assigned to Zoning Architect | 11/21/2024 | RONALD GREENE |
| Corrections Issued | 11/27/2024 | JOHNNY WU |
| Quality Review Completed | 12/16/2024 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/7/2025 | JOHNNY WU |
| Plan Check Approved | 2/7/2025 | JOHNNY WU |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 12/23/2025 | RONALD JIMENEZ |
| Permit Finaled | 12/23/2025 | ERNESTO CORRAL |
| CofO Issued | 12/23/2025 | ERNESTO CORRAL |
| Permit Finaled | 12/23/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 12/27/2024 | CHRISTINA BRACO |
| DAS Clearance | Cleared | 1/22/2025 | Samuel Gonzalez |
| Zoning Plan Check | Cleared | 1/23/2025 | Ronald Greene |
Contact Information
| Architect | Kerwin,, Jason Douglas; Lic. No.: C29140 | 10844 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Contractor | S P C Industries Inc; Lic. No.: 433163-B | , |
| Contractor | Sierra Pacific Constructors Inc; Lic. No.: 433163-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2025 | Approved | RONALD JIMENEZ |
| Light Gage Steel Frame | 3/19/2025 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 4/3/2025 | Approved | RONALD JIMENEZ |
| Insulation | 4/25/2025 | Approved | DARRYL ARNOLD |
| Light Gage Steel Frame | 4/25/2025 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 4/29/2025 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 5/9/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| T-Bar Ceiling | 5/20/2025 | Approved | RONALD JIMENEZ |
| Final | 8/29/2025 | Corrections Issued | RONALD JIMENEZ |
| Reinforced Masonry Frame | 8/29/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 8/29/2025 | Approved | RONALD JIMENEZ |
| Final | 12/15/2025 | Conditional Approval | ALFREDO LOPEZ |
| Final | 12/23/2025 | OK to Issue CofO | RONALD JIMENEZ |