4007-4009 N WESLIN AVE 91423
Certificate Information: 4007-4009 N WESLIN AVE 91423
- Application / Permit
- 24016-10000-36612
- Plan Check / Job No.
- B24LA32128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan Convert existing below 1st floor space to JADU. Convert part of the 1st floor bedroom to bath & closet.
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Current Status
- CofO Issued on 1/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 11/21/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 1/18/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 4/9/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/11/2025 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 4/22/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 4/24/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 4/27/2025 | ZAW HAN |
| Issued | 4/28/2025 | APPLICANT |
| CofO in Progress | 1/12/2026 | RAUL OLAGI |
| Permit Finaled | 1/14/2026 | RUBEN SALAS |
| Permit Finaled | 1/14/2026 | RUBEN SALAS |
| CofO Issued | 1/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2025 | CARLOS AGUILERA |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: NA36271 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/19/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 5/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 5/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 5/19/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 5/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/4/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/4/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/4/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/4/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 8/4/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 8/21/2025 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/2/2025 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 12/2/2025 | Approved | JUAN VALENZUELA |
| Wood Frame | 12/2/2025 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/18/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/18/2025 | Approved | JUAN VALENZUELA |
| Final | 12/18/2025 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 12/18/2025 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 12/18/2025 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 12/18/2025 | Approved | JUAN VALENZUELA |
| Final | 1/12/2026 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 1/12/2026 | Approved | RAUL OLAGI |