4849-4851 E AXTELL ST 90032

Certificate Information: 4849-4851 E AXTELL ST 90032

Application / Permit
24016-10000-36495
Plan Check / Job No.
B24LA31951
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Convert 3 car garage under dwelling to new attached ADU with laundry room
Permit Issued
Issued on 7/22/2025
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 ADAM HEGAZI
Corrections Issued 11/22/2024 ADAM HEGAZI
Applicant returned to address corrections 12/27/2024 CARLOS MONTES
Applicant returned to address corrections 1/2/2025 CARLOS MONTES
Plan Check Approved 7/22/2025 ADAM HEGAZI
Issued 7/22/2025 APPLICANT
CofO in Progress 7/7/2026 LILIANA PORTILLO
Permit Finaled 7/9/2026 DEROLD HAUFF
CofO Issued 7/9/2026 DEROLD HAUFF
Permit Finaled 7/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/3/2024 JUSTIN BICOL
Sewer availability Cleared 12/3/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/4/2024 JUSTIN BICOL
Tenant Habitability Plan Cleared 12/23/2024 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/27/2025 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 9/4/2025 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 9/9/2025 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 9/9/2025 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 9/9/2025 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 9/12/2025 Conditional Approval ANTHONY RAMOS
Footing/Foundation/Slab 9/12/2025 Approved LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 9/16/2025 Corrections Issued LILIANA PORTILLO
Wood Frame 9/16/2025 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 9/18/2025 Corrections Issued LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 9/18/2025 Approved LILIANA PORTILLO
Gas Test 9/23/2025 Partial Approval ANTHONY RAMOS
Insulation 9/23/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/23/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 9/26/2025 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 9/26/2025 Approved LILIANA PORTILLO
Drywall Nailing 9/30/2025 Approved REGINA MENDEZ
Gas Test 12/17/2025 Approved LILIANA PORTILLO
Service/Power Release 4/15/2026 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/11/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 5/11/2026 Corrections Issued NICHOLAS LOPEZ
Final 5/11/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 5/11/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 5/11/2026 Approved NICHOLAS LOPEZ
HVAC-Final 5/11/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 5/11/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 5/11/2026 Approved NICHOLAS LOPEZ
Smoke Detectors 5/11/2026 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 5/13/2026 Approved JOSH MEISTER
Final 5/13/2026 Not Ready for Inspection JOSH MEISTER
Green Building Final 5/13/2026 Not Ready for Inspection JOSH MEISTER
HVAC-Final 5/13/2026 Approved JOSH MEISTER
Smoke Detectors 5/13/2026 Approved JOSH MEISTER
ELECTRICAL-Final 5/14/2026 Approved OSVALDO PARAMO
Service/Power Release 5/29/2026 Approved LILIANA PORTILLO
Final 7/1/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 7/1/2026 Approved LILIANA PORTILLO
Final 7/6/2026 OK to Issue CofO LILIANA PORTILLO