20430-20432 W GRESHAM ST 91306
Certificate Information: 20430-20432 W GRESHAM ST 91306
- Application / Permit
- 24016-10000-36372
- Plan Check / Job No.
- B24LA31760
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JADU PER STATE LAW
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | MINA HABILI |
| Corrections Issued | 11/16/2024 | MINA HABILI |
| Building Plans Picked Up | 11/22/2024 | APPLICANT |
| Applicant returned to address corrections | 12/19/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 1/6/2025 | NGHI SU |
| Plan Check Approved | 1/15/2025 | DANIEL SANJUAN |
| Issued | 1/23/2025 | APPLICANT |
| CofO in Progress | 7/11/2025 | CHRIS CHRISTENSEN |
| CofO in Progress | 7/15/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/23/2025 | MICHAEL PELHAM |
| CofO Issued | 10/23/2025 | MICHAEL PELHAM |
| Permit Finaled | 10/23/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/11/2025 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/11/2025 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/21/2025 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/21/2025 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/21/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/21/2025 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 2/21/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 2/27/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 4/4/2025 | Approved | JEFFREY HARTLINE |
| Wood Frame | 4/4/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/11/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 6/17/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/17/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/17/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | ROBERT GOLD |
| Final | 6/26/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/26/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 6/26/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 7/14/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |