20430-20432 W GRESHAM ST 91306

Certificate Information: 20430-20432 W GRESHAM ST 91306

Application / Permit
24016-10000-36372
Plan Check / Job No.
B24LA31760
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JADU PER STATE LAW
Permit Issued
Issued on 1/23/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 MINA HABILI
Corrections Issued 11/16/2024 MINA HABILI
Building Plans Picked Up 11/22/2024 APPLICANT
Applicant returned to address corrections 12/19/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 1/6/2025 NGHI SU
Plan Check Approved 1/15/2025 DANIEL SANJUAN
Issued 1/23/2025 APPLICANT
CofO in Progress 7/11/2025 CHRIS CHRISTENSEN
CofO in Progress 7/15/2025 CHRIS CHRISTENSEN
Permit Finaled 10/23/2025 MICHAEL PELHAM
CofO Issued 10/23/2025 MICHAEL PELHAM
Permit Finaled 10/23/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 12/4/2024 LEE GUILBEAUX
Sewer availability Cleared 12/4/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/4/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/7/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/4/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 2/11/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 2/11/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/21/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 2/21/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 2/21/2025 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 2/21/2025 Approved CHRIS CHRISTENSEN
Wood Frame 2/21/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 2/27/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/27/2025 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 4/4/2025 Approved JEFFREY HARTLINE
Green Building Rough 4/4/2025 Approved JEFFREY HARTLINE
Wood Frame 4/4/2025 Approved JEFFREY HARTLINE
Drywall Nailing 4/11/2025 Approved CHRIS CHRISTENSEN
Final 6/17/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/17/2025 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 6/17/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Not Ready ROBERT GOLD
Final 6/26/2025 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 6/26/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 6/26/2025 Approved CHRIS CHRISTENSEN
Final 7/14/2025 OK to Issue CofO CHRIS CHRISTENSEN