6058 W 83RD PL 90045
Certificate Information: 6058 W 83RD PL 90045
- Application / Permit
- 24016-10000-36367
- Plan Check / Job No.
- B24LA31757
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING REC ROOM THAT IS ATTACHED TO A GARAGE TO AN ADU. WORK PER WFPP. DETACHED ADU PER 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), & (g).
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | ADRIANA LOPEZ |
| Corrections Issued | 12/9/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 12/12/2024 | KEN GILL |
| Building Plans Picked Up | 12/17/2024 | APPLICANT |
| Applicant returned to address corrections | 2/12/2025 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 3/26/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 5/15/2025 | ADRIANA LOPEZ |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 9/5/2025 | JESUS PINEDA |
| No Progress | 9/8/2025 | DAVID FEILER |
| CofO in Progress | 9/8/2025 | DAVID FEILER |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
| CofO Issued | 9/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/21/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/21/2025 | RIDWAN HARDY |
| Address approval | Cleared | 4/15/2025 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2025 | DIANA RENTERIA |
| Sewer availability | Cleared | 4/15/2025 | DIANA RENTERIA |
| Specific Plan | Cleared | 4/29/2025 | EDER ROMERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/21/2025 | Partial Inspection | ARAM AVEDISIAN |
| Pre-Inspection | 6/17/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 7/7/2025 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 7/8/2025 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 7/8/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/8/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 7/18/2025 | Approved | JESUS PINEDA |
| Insulation | 7/18/2025 | Approved | JESUS PINEDA |
| Rough-Elec/Plmb/HVAC | 7/18/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 7/25/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/19/2025 | Approved | JESUS PINEDA |
| Final | 8/19/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/19/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/19/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/19/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 8/19/2025 | Approved | JESUS PINEDA |
| Final | 9/5/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 9/5/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/5/2025 | Approved | JESUS PINEDA |