1663 N AVALON BLVD Unit 1-26 90744
Certificate Information: 1663 N AVALON BLVD Unit 1-26 90744
- Application / Permit
- 24016-10000-36259
- Plan Check / Job No.
- B24LA31635
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Convert attached recroom in an existing apartment to an ADU (500 SF) per CA Govt. Code 65852.2(e)(1)(C).
- Permit Issued
- Issued on 4/1/2025
- Issuing Office
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | DANIEL SMILEY |
| Corrections Issued | 11/14/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 12/4/2024 | EDWIN MARTINEZ |
| Plan Check Approved | 1/29/2025 | JOHNPAUL ISIP |
| Issued | 4/1/2025 | APPLICANT |
| CofO in Progress | 5/15/2026 | DAVID TSAU |
| Permit Finaled | 5/15/2026 | DAVID TSAU |
| CofO Issued | 5/15/2026 | DAVID TSAU |
| Permit Finaled | 5/15/2026 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/20/2024 | MAYELA VILLA |
| Address approval | Cleared | 11/21/2024 | CELINA MORENO |
| Sewer availability | Cleared | 11/21/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | CELINA MORENO |
| Fire Marshal Fire Life Safety | Cleared | 1/6/2025 | DOMINIQUE MEDINA |
Contact Information
| Contractor | Ramos Remodeling Construction Cor; Lic. No.: 1116644-B | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 5/15/2025 | Corrections Issued | MICHAEL PETRUSKO |
| Wood Frame | 5/20/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 9/17/2025 | Partial Approval | RICARDO ROBLES |
| METHANE-Final | 9/17/2025 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 9/17/2025 | Approved | RICARDO ROBLES |
| Final | 5/4/2026 | Partial Inspection | DAVID TSAU |
| Final | 5/13/2026 | Partial Inspection | DAVID TSAU |