1229 N SHADYBROOK DR 90210

Certificate Information: 1229 N SHADYBROOK DR 90210

Application / Permit
24016-10000-36122
Plan Check / Job No.
B24LA31472
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing detached garage to new ADU per engineer design. (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 1/9/2025
Issuing Office
Current Status
CofO Issued on 9/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 AUNG SOE
Corrections Issued 12/3/2024 AUNG SOE
Applicant returned to address corrections 12/12/2024 NEHEMIAS RAMOS
Plan Check Approved 1/7/2025 NEHEMIAS RAMOS
Issued 1/9/2025 APPLICANT
CofO in Progress 9/25/2025 SEAN HAUPT
Permit Finaled 9/29/2025 RICHARD STEINBACH
CofO Issued 9/29/2025 RICHARD STEINBACH
Permit Finaled 9/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/18/2024 ANTHONY MAINEZ
Sewer availability Cleared 11/18/2024 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/21/2024 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 11/26/2024 MANUEL TEJADA
Hold Cleared 2/3/2025 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/7/2025 Approved SEAN HAUPT
Underground Mechanical 5/7/2025 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 5/20/2025 Approved SEAN HAUPT
Footing/Foundation/Slab 5/20/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/24/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/24/2025 Approved STEPHANIE SWANSON
Green Building Rough 6/24/2025 Approved STEPHANIE SWANSON
HVAC-Rough 6/24/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 6/24/2025 Conditional Approval STEPHANIE SWANSON
PLUMBING-Rough 6/24/2025 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/1/2025 Approved SEAN HAUPT
HVAC-Rough 7/1/2025 Approved SEAN HAUPT
Insulation 7/1/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 7/1/2025 Partial Approval SEAN HAUPT
PLUMBING-Rough 7/1/2025 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved SEAN HAUPT
Special/Order Compliance 7/8/2025 Partial Approval SEAN HAUPT
Drywall Nailing 7/17/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 7/17/2025 Approved SEAN HAUPT
Shower Pan 7/17/2025 Approved SEAN HAUPT
Final 9/19/2025 Corrections Issued SEAN HAUPT
Green Building Final 9/19/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Approved SEAN HAUPT
Smoke Detectors 9/19/2025 Approved SEAN HAUPT
ELECTRICAL-Final 9/23/2025 Approved SEAN HAUPT
Final 9/23/2025 OK to Issue CofO SEAN HAUPT
Green Building Final 9/23/2025 Approved SEAN HAUPT
HVAC-Final 9/23/2025 Approved SEAN HAUPT
PLUMBING-Final 9/23/2025 Approved SEAN HAUPT