5024 E EATON ST 90042

Certificate Information: 5024 E EATON ST 90042

Application / Permit
24016-10000-35934
Plan Check / Job No.
B24LA31288
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: ( E ) GARAGE CONVERSION TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2024 APPLICANT
Assigned to Plan Check Engineer 12/3/2024 MOHAMMAD ESMAILI
Corrections Issued 12/12/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/26/2025 MOHAMMAD ESMAILI
Plan Check Approved 3/6/2025 MOHAMMAD ESMAILI
Issued 3/10/2025 APPLICANT
CofO in Progress 8/26/2025 DAVID WILLIAMS
Permit Finaled 8/27/2025 DEROLD HAUFF
CofO Issued 8/27/2025 DEROLD HAUFF
Permit Finaled 8/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2024 KEVIN AVILA
Sewer availability Cleared 12/14/2024 KEVIN AVILA
Eng Process Fee Ord 176,300 Cleared 3/5/2025 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Chiang,, Tzuu Pien; Lic. No.: C72618 18295 AGUIRO STREET      ROWLAND HEIGHTS, CA 91748

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/23/2025 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 4/24/2025 Approved DAVID WILLIAMS
Sewer 4/24/2025 Approved DAVID WILLIAMS
Underground Mechanical 4/24/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 5/19/2025 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 5/19/2025 Approved BRENDAN MORELLI
HVAC-Rough 5/19/2025 Approved BRENDAN MORELLI
PLUMBING-Rough 5/19/2025 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 6/4/2025 Conditional Approval REGINA MENDEZ
Insulation 6/4/2025 Approved REGINA MENDEZ
PLUMBING-Rough 6/4/2025 Conditional Approval REGINA MENDEZ
Drywall Nailing 6/11/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/11/2025 Approved REGINA MENDEZ
Final 8/7/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 8/7/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV No Gas DAVID WILLIAMS
Smoke Detectors 8/7/2025 Approved DAVID WILLIAMS
Final 8/19/2025 Corrections Issued LILIANA PORTILLO
Final 8/22/2025 Not Ready for Inspection DAVID WILLIAMS
Final 8/26/2025 OK to Issue CofO DAVID WILLIAMS
Final 10/14/2025 OK to Issue CofO DAVID WILLIAMS