7353 W 83RD ST 90045

Certificate Information: 7353 W 83RD ST 90045

Application / Permit
24016-10000-35895
Plan Check / Job No.
B24LA31251
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Convert detached carport to ADU per state law. All work per engineering.
Permit Issued
Issued on 9/22/2025
Issuing Office
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 DANIEL SMILEY
Corrections Issued 11/18/2024 DANIEL SMILEY
Plan Check Approved 2/24/2025 JOHN MESIAS
Issued 9/22/2025 APPLICANT
CofO in Progress 3/19/2026 JESUS PINEDA
Permit Finaled 4/3/2026 RICHARD STEINBACH
CofO Issued 4/3/2026 RICHARD STEINBACH
Permit Finaled 4/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/26/2024 LIAM ODONOVAN
Sewer availability Cleared 11/26/2024 LIAM ODONOVAN
Grading Pre-Inspection Cleared 11/26/2024 MATTHEW JENKINS
Eng Process Fee Ord 176,300 Cleared 12/2/2024 LIAM ODONOVAN
Specific Plan Cleared 12/2/2024 PEDRO AYALA
Construction near power lines Cleared 1/25/2025 RIDWAN HARDY
Construction within easement Cleared 1/25/2025 RIDWAN HARDY

Contact Information

Contractor Ayon Construction; Lic. No.: 1044491-B       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/30/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 10/21/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/27/2025 Approved JESUS PINEDA
PLUMBING-Rough 10/27/2025 Partial Approval JESUS PINEDA
Sewer 10/27/2025 Approved JESUS PINEDA
Underground Mechanical 10/27/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/31/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 10/31/2025 Approved JESUS PINEDA
HVAC-Rough 10/31/2025 Approved JESUS PINEDA
PLUMBING-Rough 10/31/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 11/7/2025 Approved JESUS PINEDA
Insulation 11/7/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 11/7/2025 Approved JESUS PINEDA
Shower Pan 11/7/2025 Approved JESUS PINEDA
Drywall Nailing 11/12/2025 Approved JESUS PINEDA
ELECTRICAL-Final 12/29/2025 Corrections Issued JESUS PINEDA
Final 12/29/2025 Corrections Issued JESUS PINEDA
HVAC-Final 12/29/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 12/29/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 1/13/2026 Approved JESUS PINEDA
Final 1/13/2026 Corrections Issued JESUS PINEDA
HVAC-Final 1/13/2026 Approved JESUS PINEDA
PLUMBING-Final 1/13/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved JESUS PINEDA
Smoke Detectors 1/13/2026 Approved JESUS PINEDA
Final 3/19/2026 OK to Issue CofO JESUS PINEDA