8652 W OLIN ST 90034
Certificate Information: 8652 W OLIN ST 90034
- Application / Permit
- 24016-10000-35830
- Plan Check / Job No.
- B24LA31162
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ADU PER GCS65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/7/2025
- Issuing Office
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | DANIEL SMILEY |
| Corrections Issued | 11/18/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 12/26/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 1/5/2025 | ALEC MOUSAKHANIAN |
| Issued | 1/7/2025 | APPLICANT |
| CofO in Progress | 5/2/2025 | MEL KHACHATOURIAN |
| Permit Finaled | 5/6/2025 | RICHARD STEINBACH |
| CofO Issued | 5/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/23/2024 | JUSTIN BICOL |
| ZA Case | Cleared | 11/27/2024 | YINGSHI HUANG |
| Address approval | Cleared | 12/12/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Pacific Point Builders Inc; Lic. No.: 768984-B | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/27/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 1/27/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 1/27/2025 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 1/31/2025 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 2/5/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/5/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/20/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| MERV13>=Rough | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/26/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 2/28/2025 | Approved | ARAM AVEDISIAN |
| Sewer | 3/3/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 3/6/2025 | Approved | AMY COLIN |
| Shower Pan | 3/6/2025 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 3/10/2025 | Approved | KIRK SANDERS |
| Final | 5/1/2025 | OK to Issue CofO | MEL KHACHATOURIAN |
| Green Building Final | 5/1/2025 | Approved | MEL KHACHATOURIAN |
| MERV13>=Final | 5/1/2025 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 5/1/2025 | Approved | MEL KHACHATOURIAN |