9298-9300 N TAMARACK AVE 91352
Certificate Information: 9298-9300 N TAMARACK AVE 91352
- Application / Permit
- 24016-10000-35653
- Plan Check / Job No.
- B24VN20036
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- convert (E) attached garage to JADU per CA Govt. Code 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 2/7/2025
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 11/7/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 11/8/2024 | RODOLFO ARIAS |
| Plan Check Approved | 2/4/2025 | GEORGE JOLAKIAN |
| Issued | 2/7/2025 | APPLICANT |
| CofO in Progress | 9/3/2025 | MATTHEW NELSON |
| CofO Issued | 9/18/2025 | RUBEN SALAS |
| Permit Finaled | 9/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/13/2024 | BIAINA HARITUNIAN |
| Certificate of Compliance | Cleared | 1/14/2025 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2025 | Corrections Issued | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 3/5/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/7/2025 | Approved | MATTHEW NELSON |
| Pre-Inspection | 3/7/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/23/2025 | Approved | DAVID MATSON |
| Wood Frame | 4/23/2025 | Approved | DAVID MATSON |
| Insulation | 4/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 4/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/30/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Final | 8/28/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/28/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 8/28/2025 | Approved | MATTHEW NELSON |
| Final | 9/2/2025 | OK to Issue CofO | MATTHEW NELSON |