5442 S 8TH AVE 90043
Certificate Information: 5442 S 8TH AVE 90043
- Application / Permit
- 24016-10000-35509
- Plan Check / Job No.
- B24LA30740
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Ground addition to (E) 1-story signle family dwelling
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | KHEDER ALRAZAA |
| Corrections Issued | 12/2/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 12/4/2024 | GARO TELMI |
| Plan Check Approved | 1/21/2025 | KHEDER ALRAZAA |
| Issued | 1/23/2025 | APPLICANT |
| CofO in Progress | 2/26/2026 | LUIS CASTRO |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
| Permit Finaled | 2/27/2026 | DEROLD HAUFF |
| CofO Issued | 2/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/9/2024 | CELINA MORENO |
| Sewer availability | Cleared | 12/9/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 3/7/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 3/10/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 3/10/2025 | Partial Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 3/26/2025 | Partial Approval | LUIS CASTRO |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 5/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 5/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 5/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 5/30/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 5/30/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 6/3/2025 | Approved | ANTHONY RAMOS |
| PLUMBING-Rough | 6/3/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 6/9/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 6/9/2025 | Approved | LUIS CASTRO |
| Insulation | 6/9/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 6/9/2025 | Partial Approval | LUIS CASTRO |
| Drywall Nailing | 6/17/2025 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/17/2025 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/21/2025 | Approved | STUART CHAPMAN |
| Final | 11/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 11/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 11/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 12/15/2025 | Approved | LUIS CASTRO |
| Final | 12/15/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 12/15/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 12/15/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 12/15/2025 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 12/15/2025 | Corrections Issued | LUIS CASTRO |
| Final | 1/27/2026 | Partial Approval | LUIS CASTRO |
| Green Building Final | 1/27/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 1/27/2026 | Approved | LUIS CASTRO |
| Final | 1/29/2026 | Corrections Issued | LUIS CASTRO |
| Final | 2/13/2026 | Conditional Approval | LUIS CASTRO |
| PLUMBING-Final | 2/13/2026 | Approved | LUIS CASTRO |
| Final | 2/25/2026 | OK to Issue CofO | LUIS CASTRO |