5442 S 8TH AVE 90043

Certificate Information: 5442 S 8TH AVE 90043

Application / Permit
24016-10000-35509
Plan Check / Job No.
B24LA30740
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Ground addition to (E) 1-story signle family dwelling
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO Issued on 2/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 KHEDER ALRAZAA
Corrections Issued 12/2/2024 KHEDER ALRAZAA
Quality Review Completed 12/4/2024 GARO TELMI
Plan Check Approved 1/21/2025 KHEDER ALRAZAA
Issued 1/23/2025 APPLICANT
CofO in Progress 2/26/2026 LUIS CASTRO
Permit Finaled 2/27/2026 DEROLD HAUFF
Permit Finaled 2/27/2026 DEROLD HAUFF
CofO Issued 2/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/9/2024 CELINA MORENO
Sewer availability Cleared 12/9/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/10/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/20/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 3/7/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Partial Approval LUIS CASTRO
Insulation 3/10/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 3/10/2025 Partial Approval LUIS CASTRO
Deputy Drilled-In Anchors 3/26/2025 Partial Approval LUIS CASTRO
Service/Power Release 4/2/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 5/14/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval LUIS CASTRO
Green Building Rough 5/14/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 5/14/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 5/30/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 5/30/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 6/3/2025 Approved ANTHONY RAMOS
PLUMBING-Rough 6/3/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 6/9/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Approved LUIS CASTRO
Green Building Rough 6/9/2025 Approved LUIS CASTRO
Insulation 6/9/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 6/9/2025 Partial Approval LUIS CASTRO
Drywall Nailing 6/17/2025 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/17/2025 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 7/21/2025 Approved STUART CHAPMAN
Final 11/26/2025 Not Ready for Inspection LUIS CASTRO
Green Building Final 11/26/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 11/26/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 12/15/2025 Approved LUIS CASTRO
Final 12/15/2025 Corrections Issued LUIS CASTRO
Green Building Final 12/15/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Final 12/15/2025 Approved LUIS CASTRO
PLUMBING-Final 12/15/2025 Corrections Issued LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/15/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 12/15/2025 Corrections Issued LUIS CASTRO
Final 1/27/2026 Partial Approval LUIS CASTRO
Green Building Final 1/27/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 1/27/2026 Approved LUIS CASTRO
Final 1/29/2026 Corrections Issued LUIS CASTRO
Final 2/13/2026 Conditional Approval LUIS CASTRO
PLUMBING-Final 2/13/2026 Approved LUIS CASTRO
Final 2/25/2026 OK to Issue CofO LUIS CASTRO